Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Louisiana retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Louisiana retainage law: cap, release deadline and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

Louisiana caps retainage only on public works. A public entity cannot withhold more than 10% of the contract price on projects under $500,000, or 5% on projects of $500,000 or more, and only until 45 days after formal acceptance of the work is recorded (R.S. 38:2248). The owner must record acceptance within 30 days of substantial completion. Private jobs have no retainage statute at all, so the percentage and release date come from the contract, enforced through lien and prompt-payment rights.

## Retainage on private jobs

**No statute.** Louisiana has no statute capping, requiring or timing retainage on private jobs. The Private Works Act (R.S. 9:4801 et seq.) governs liens, not retainage: a sub's remedy is a statement of claim or privilege filed within 60 days after a notice of termination or substantial completion (30 days / six months if a notice of contract was filed), and retainage terms are whatever the contract says. The 1.5% per month penalty in R.S. 9:2784 applies to retainage that is overdue under the contract.

## Retainage on public jobs

| Rule | Louisiana law |
|---|---|
| Retainage cap | 10% on contracts under $500,000; 5% on contracts of $500,000 or more ([La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968)) |
| Release deadline | 45 days Payment may be withheld only until 45 days after recordation of formal acceptance of the work (or notice of default); punch list withholding limited to the estimated value of the punch list items (R.S. 38:2248). Owner must record acceptance within 30 calendar days of substantial completion (R.S. 38:2241.1) ([La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968)) |
| Interest on late retainage | Late final payment: 0.5% per day accumulated, capped at 15%, plus attorney fees (R.S. 38:2191(B)(1)) ([La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968)) |
| Applies to local governments | Yes ([La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968)) |

## When the GC says it hasn't been paid in Louisiana

Under R.S. 9:2784(B), a GC must pay a sub the sub's share within 7 days after the GC itself is paid, including accrued interest. If the owner has not paid the GC, the 7-day clock has not started, but the GC must still pay any undisputed amount by the applicable date (R.S. 9:2784(C)) and a good-faith dispute only lets the GC withhold the disputed part. A waiver of any provision of the section is absolutely null (R.S. 9:2784(E)).

## After the deadline: what a sub can do in Louisiana

Private job: send written demand on day 8 after the GC was paid, claiming the 1.5% per month penalty, and sue under R.S. 9:2784(F) for the payment, penalty and attorney fees. Preserve the lien: file a statement of claim within 60 days after the notice of termination or substantial completion, or within 30 days / six months if a notice of contract was filed (R.S. 9:4822). Public job: if the entity withholds contested liquidated damages or sits on a payment, seek mandamus under R.S. 38:2191 (fees and interest included since Act 255 of 2026); serve notice and sue on the payment bond under R.S. 38:2242 and 38:2247 (written notice to the GC within 45 days of recorded acceptance for lower-tier claimants).

## Louisiana quirks to know

Act 822 of 2026 rewrote R.S. 9:2784 from August 1, 2026: a new 35-day owner clock, 7 days instead of 14 for each tier to pay the next, an uncapped 1.5% a month instead of 0.5% a day capped at 15%, waivers null, and the blanket residential exclusion dropped (single-family contracts may allow up to 61 days). The public side still runs 0.5% a day, capped at 15%. Since May 15, 2026 (Act 255) a public owner cannot withhold contested liquidated damages from progress or final payments. The 35-day private clock extends to the fifth day after loan proceeds arrive when the owner has a construction loan. The public retainage section does not apply to DOTD and cannot be waived (R.S. 38:2248(B)(3)). Louisiana's 'privilege' is its lien.

## Worked example: retainage on a $480,000 subcontract in Louisiana

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | August 15, 2026 |
| Public job: owner releases by | September 29, 2026 ([La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Louisiana public works contract of $480,000 (under $500,000, so the 10% cap applies, R.S. 38:2248(A)): retainage is $48,000. Substantial completion 2026-08-15 (after Act 822 took effect, so the private prompt-pay example on this page uses the new 7-day rule); acceptance recorded by 2026-09-14 (30 days, R.S. 38:2241.1). The entity may hold the retainage only until 2026-10-29 (45 days after recordation). If it pays 20 days late, interest at 0.5% per day is 10% of the amount, $4,800; the 15% cap ($7,200) is reached at 30 days late. Interest is shared pro rata with subs within 10 business days of receipt (R.S. 38:2191(B)(2)).

## Louisiana retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/louisiana/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 45 days (Payment may be withheld only until 45 days after recordation of formal acceptance of the work (or notice of default); punch list withholding limited to the estimated value of the punch list items (R.S. 38:2248). Owner must record acceptance within 30 calendar days of substantial completion (R.S. 38:2241.1)); interest: Late final payment: 0.5% per day accumulated, capped at 15%, plus attorney fees (R.S. 38:2191(B)(1)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Louisiana retainage law: questions

### What is the retainage limit on a Louisiana public works contract?

10% of the contract price on projects under $500,000 and 5% on projects of $500,000 or more, held only until 45 days after recordation of formal acceptance (R.S. 38:2248(A)).

### Is there a retainage cap on private construction in Louisiana?

No. Retainage on a private Louisiana job is set by the contract; the Private Works Act contains no cap or release date.

## Sources

- [La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Louisiana prompt payment law](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- Louisiana
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)