title: "Michigan Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Michigan retainage: no statute on private jobs, the subcontract governs; public jobs of $30K+ cap 10%, release within 30 days. Statute and a calculator."
url: "/construction/retainage/michigan/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Michigan retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Michigan retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Michigan regulates retainage only on public agency contracts. Under Act 524 of 1980, a public agency may withhold no more than 10% of the value of work in place until the job is 50% in place and, after that, no further retainage unless progress is unsatisfactory or there is other specific cause. Retained funds sit in a separate interest-bearing account and are released with the interest on the final progress payment. Private jobs have no retainage statute: the contract sets the percentage and the release date.

## Retainage on private jobs

**No statute.** Michigan has no statute that caps, requires or times retainage on private jobs. The Construction Lien Act mentions retainage only to say that retainage not payable until some further event is not 'due' on the date of the improvement (MCL 570.1115, 570.1119). Percentage and release date are whatever the prime contract and subcontract say.

## Retainage on public jobs

| Rule | Michigan law |
|---|---|
| Retainage cap | 10% on contracts of $30,000 or more ([Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)) |
| Release deadline | 30 days Retainage and interest earned on it are released to the contractor together with the final progress payment (due on the later of 30 days after the architect/engineer certifies work in place or 15 days after the agency receives funding). After 94% of the work is in place the contractor can obtain release of retainage plus interest by posting an irrevocable letter of credit in that amount ([Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)) |
| Interest on late retainage | Retained funds must not be commingled and must sit in an interest-bearing account in a regulated financial institution in Michigan, accounted for per contract, and are released with the interest earned; no deposit is required while grant-funded retainage has not been paid to the agency, and retained funds may not exceed the pro rata share of the agency's matching requirement. Interest earned during a delay found by the agent belongs to the agency (MCL 125.1563(3), 125.1564(7)). ([Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)) |
| Retainage bond in lieu | Irrevocable letter of credit from a bank authorised in Michigan once 94% of the work is in place (MCL 125.1563(5)) ([Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)) |
| Applies to local governments | Yes ([Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)) |

## When the GC says it hasn't been paid in Michigan

On a private Michigan job, a pay-if-paid or pay-when-paid clause is a contract matter: no prompt-pay statute overrides it, and the Construction Lien Act treats retainage that is payable only after a further event as 'not due' until then (MCL 570.1115(5), 570.1119(5)). A 2010 bill to ban pay-when-paid clauses in public-works bonding (Senate Bill 1319, amending 1963 PA 213) was only referred to committee and never enacted, so Michigan has no statutory pay-if-paid ban on public or private work.

## After the deadline: what a sub can do in Michigan

Private job: send written demand citing the contract and protect your construction lien: serve a notice of furnishing and record a claim of lien within the Construction Lien Act deadlines. Public job: sue on the payment bond; the claimant must have served written notice on the principal contractor within 30 days after first furnishing labor or materials and given written notice to the contractor and the governmental unit within 90 days after last furnishing, and may sue after 90 days unpaid and within one year of final payment (MCL 129.207, 129.209).

## Michigan quirks to know

Act 524 applies only to contracts with public agencies of $30,000 or more with more than three payments and excludes MDOT, school districts, community colleges, MSHDA and municipal electric utilities. Agencies must put retainage in a separate interest-bearing account and account for it per contract. A dispute-resolution 'agent' may rule on contractor delay and decide who gets the interest earned on retainage. The statutory interest on a late progress payment is 'reasonable interest', not a number. Retained funds may not exceed the agency's pro rata matching share, and grant-funded retainage need not be deposited until the grant money arrives (125.1563(3)).

## Worked example: retainage on a $480,000 subcontract in Michigan

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 15, 2026 ([Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Michigan public agency contract, $480,000 (above the $30,000 threshold): retainage may be taken at up to 10% of work in place until the job is 50% in place, so the normal maximum is 10% of $240,000 = $24,000 (MCL 125.1563(2)); more only if the agency finds unsatisfactory progress. Work certified complete 2026-06-15: the final progress payment, with the retainage and its interest, is due by the later of 2026-07-15 (30 days after the architect's certification) or 15 days after the agency receives any state or federal funding (MCL 125.1562(3), 125.1563(4)). The statute fixes no interest rate beyond 'reasonable interest', so no dollar interest is computed.

## Michigan retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/michigan/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 30 days (Retainage and interest earned on it are released to the contractor together with the final progress payment (due on the later of 30 days after the architect/engineer certifies work in place or 15 days after the agency receives funding). After 94% of the work is in place the contractor can obtain release of retainage plus interest by posting an irrevocable letter of credit in that amount); interest: Retained funds must not be commingled and must sit in an interest-bearing account in a regulated financial institution in Michigan, accounted for per contract, and are released with the interest earned; no deposit is required while grant-funded retainage has not been paid to the agency, and retained funds may not exceed the pro rata share of the agency's matching requirement. Interest earned during a delay found by the agent belongs to the agency (MCL 125.1563(3), 125.1564(7))..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Michigan retainage law: questions

### Is there a retainage law for private construction in Michigan?

No. Michigan has no private retainage cap or release deadline; the Construction Lien Act only addresses how retainage is treated for lien priority (MCL 570.1119).

### What is the retainage limit on a Michigan public contract?

Not more than 10% of the value of work in place until the work is 50% in place; after that, none unless the agency finds unsatisfactory progress or other cause for the contractor's performance (MCL 125.1563(2)).

### When must a Michigan public agency release retainage?

With the final progress payment, together with the interest earned on it; the contractor can also get early release after 94% completion by posting an irrevocable letter of credit (MCL 125.1563(4)-(5)).

## Sources

- [Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Michigan prompt payment law](https://fynex.ai/construction/prompt-payment/michigan/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- Michigan
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)