Minnesota retainage law: cap, release deadline and interest
Minnesota caps retainage at 5% on both private and public building and construction contracts, and the owner must release all of it within 60 days after substantial completion (Minn. Stat. 337.10 subd. 4; 15.72 subd. 2 for public improvements). The GC must pay each sub's retainage within 10 days after receiving it. After substantial completion the owner may keep back 250% of known correction costs plus the greater of 1% of the contract or $500 until the final paperwork is in. Retainage for warranty work is prohibited.
Also in Minnesota: prompt payment law
Minnesota retainage release date and interest calculator
Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Minnesota law; change them if your contract or the statute's trigger differs.
Clock starts: Owner must release all retainage no later than 60 days after substantial completion (as defined in Minn. Stat. 541.051 subd. 1(a): sufficiently complete that the owner can occupy or use the improvement for its intended purpose). After substantial completion the owner may withhold no more than 250% of the cost to correct or complete known work, plus the greater of 1% of the contract value or $500 until final paperwork is submitted (paid within 60 days after submission). Retainage for warranty work is prohibited
Statute: Late retainage to subs: 1.5% per month on undisputed amounts, minimum $10 (337.10 subd. 3, which covers payments under subd. 4)
- Owner releases by
- August 14, 2026
- GC pays the sub's share by
- August 24, 2026
- Days late
- 30
- Interest owed
- —
- Total now owed
- $24,000.00
No fixed statutory rate: enter the rate from the statute or your contract.
Statute: Minn. Stat. §337.10 subd. 4
Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Retainage on private jobs
| Rule | Minnesota law |
|---|---|
| Retainage cap | 5% of each paymentMinn. Stat. §337.10 subd. 4 |
| How the cap applies | Owner or its agent may reduce or eliminate retainage on any monthly payment if work is progressing satisfactorily; if the owner reduces it, the contractor must reduce subs' retainage at the same rate. Nothing requires retainage to be withheld at all (337.10 subd. 4(b))Minn. Stat. §337.10 subd. 4 |
| Release deadline | 60 days Owner must release all retainage no later than 60 days after substantial completion (as defined in Minn. Stat. 541.051 subd. 1(a): sufficiently complete that the owner can occupy or use the improvement for its intended purpose). After substantial completion the owner may withhold no more than 250% of the cost to correct or complete known work, plus the greater of 1% of the contract value or $500 until final paperwork is submitted (paid within 60 days after submission). Retainage for warranty work is prohibitedMinn. Stat. §337.10 subd. 4 |
| GC passes the sub's share within | 10 days of receiving itMinn. Stat. §337.10 subd. 4 |
| Interest on late retainage | Late retainage to subs: 1.5% per month on undisputed amounts, minimum $10 (337.10 subd. 3, which covers payments under subd. 4)Minn. Stat. §337.10 subd. 4 |
Retainage on public jobs
| Rule | Minnesota law |
|---|---|
| Retainage cap | 5% of each paymentMinn. Stat. §15.72 subd. 2 (public improvements); §15.71 |
| Release deadline | 60 days Public contracting agency must release all retainage no later than 60 days after substantial completion; may then withhold no more than 250% of the cost to correct or complete known work and the greater of 1% of the contract value or $500 pending final paperwork; contractor pays subs' retainage within 10 days after receiving it. For streets, highways and bridges, substantial completion is when construction-related traffic devices and ongoing inspections are no longer requiredMinn. Stat. §15.72 subd. 2 (public improvements); §15.71 |
| Prime passes the sub's share within | 10 days of receiving itMinn. Stat. §15.72 subd. 2 (public improvements); §15.71 |
| Interest on late retainage | Subcontractor interest 1.5% per month (471.425 subd. 4a; 337.10 subd. 3). Agency interest on retainage is not stated in 15.72Minn. Stat. §15.72 subd. 2 (public improvements); §15.71 |
| Applies to local governments | YesMinn. Stat. §15.72 subd. 2 (public improvements); §15.71 |
When the GC says it hasn't been paid in Minnesota
Minnesota keys the sub's 10 days to the GC receiving payment from the party responsible for payment, so the GC cannot stretch it without having been paid. Undisputed amounts only: a GC with a real dispute about a sub's work must still pay out retainage to subs whose work is not involved and give a written statement of the amount and reason (337.10 subd. 4(d)). A contract cannot require a lien or payment-bond claim waiver before you have been paid (337.10 subd. 2).
After the deadline: what a sub can do in Minnesota
If an undisputed payment is not received within 10 days, you may suspend work until it arrives (337.10 subd. 3). Demand the amount plus 1.5% per month interest, and note that a prevailing party in a civil action to collect the penalties must be awarded costs, disbursements and attorney fees. Keep the mechanic's lien notice and claim deadlines running in parallel. On public work, request payment information in writing: from 2026 (Laws 2026 ch. 90) the agency must give you the amount, date and pay application copy within 7 calendar days.
Minnesota quirks to know
State agency interest does not apply to construction contractor claims (16A.124 subd. 5(e)), but municipalities owe 1.5% per month under 471.425. The same 5% / 60 / 10-day retainage rules appear twice, in 337.10 for private jobs and in 15.72 for public improvements (337.10 subd. 4(g) carves public agencies out). Federal- or state-aid projects: the agency need not pay the aided portion until the aid is received (15.72 subd. 2(h)). Maintenance or repair of production machinery and utility equipment is outside the definition of a building and construction contract.
Worked example: retainage on a $480,000 subcontract in Minnesota
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | August 14, 2026Minn. Stat. §337.10 subd. 4 |
| GC pays the sub's share by | August 24, 2026Minn. Stat. §337.10 subd. 4 |
| Interest if paid 30 days late | No statutory rate; the contract governs |
Minnesota private commercial job, $480,000 contract with the 5% maximum (337.10 subd. 4(b)): retainage is $24,000. Substantial completion 2026-06-15: the owner must release all retainage by 2026-08-14 (60 days, subd. 4(c)), less any permitted withholding (250% of correction costs; the greater of 1% of the contract, $4,800, or $500 until final paperwork). The GC then has 10 days, to 2026-08-24, to pay the sub's retainage. If the GC pays 30 days late, interest at 1.5% per month on $24,000 is about $360 (minimum $10 a month).
Minnesota retainage law: questions
What is the maximum retainage in Minnesota?
5% on private contracts (Minn. Stat. 337.10 subd. 4(b)) and 5% of each progress payment on public improvements (15.72 subd. 2(a)).
When must Minnesota retainage be released?
No later than 60 days after substantial completion, less 250% of known correction costs and the greater of 1% of the contract or $500 for outstanding paperwork (337.10 subd. 4(c), (e)).
Sources