---
title: "Minnesota Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Minnesota retainage: private jobs cap 5%, release within 60 days; public jobs cap 5%, release within 60 days. Statute, release dates and a calculator."
url: "/construction/retainage/minnesota/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Minnesota retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Minnesota retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Minnesota caps retainage at 5% on both private and public building and construction contracts, and the owner must release all of it within 60 days after substantial completion (Minn. Stat. 337.10 subd. 4; 15.72 subd. 2 for public improvements). The GC must pay each sub's retainage within 10 days after receiving it. After substantial completion the owner may keep back 250% of known correction costs plus the greater of 1% of the contract or $500 until the final paperwork is in. Retainage for warranty work is prohibited.

## Retainage on private jobs

| Rule | Minnesota law |
|---|---|
| Retainage cap | 5% of each payment ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| How the cap applies | Owner or its agent may reduce or eliminate retainage on any monthly payment if work is progressing satisfactorily; if the owner reduces it, the contractor must reduce subs' retainage at the same rate. Nothing requires retainage to be withheld at all (337.10 subd. 4(b)) ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Release deadline | 60 days Owner must release all retainage no later than 60 days after substantial completion (as defined in Minn. Stat. 541.051 subd. 1(a): sufficiently complete that the owner can occupy or use the improvement for its intended purpose). After substantial completion the owner may withhold no more than 250% of the cost to correct or complete known work, plus the greater of 1% of the contract value or $500 until final paperwork is submitted (paid within 60 days after submission). Retainage for warranty work is prohibited ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| GC passes the sub's share within | 10 days of receiving it ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Interest on late retainage | Late retainage to subs: 1.5% per month on undisputed amounts, minimum $10 (337.10 subd. 3, which covers payments under subd. 4) ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |

## Retainage on public jobs

| Rule | Minnesota law |
|---|---|
| Retainage cap | 5% of each payment ([Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72)) |
| Release deadline | 60 days Public contracting agency must release all retainage no later than 60 days after substantial completion; may then withhold no more than 250% of the cost to correct or complete known work and the greater of 1% of the contract value or $500 pending final paperwork; contractor pays subs' retainage within 10 days after receiving it. For streets, highways and bridges, substantial completion is when construction-related traffic devices and ongoing inspections are no longer required ([Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72)) |
| Prime passes the sub's share within | 10 days of receiving it ([Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72)) |
| Interest on late retainage | Subcontractor interest 1.5% per month (471.425 subd. 4a; 337.10 subd. 3). Agency interest on retainage is not stated in 15.72 ([Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72)) |
| Applies to local governments | Yes ([Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72)) |

## When the GC says it hasn't been paid in Minnesota

Minnesota keys the sub's 10 days to the GC receiving payment from the party responsible for payment, so the GC cannot stretch it without having been paid. Undisputed amounts only: a GC with a real dispute about a sub's work must still pay out retainage to subs whose work is not involved and give a written statement of the amount and reason (337.10 subd. 4(d)). A contract cannot require a lien or payment-bond claim waiver before you have been paid (337.10 subd. 2).

## After the deadline: what a sub can do in Minnesota

If an undisputed payment is not received within 10 days, you may suspend work until it arrives (337.10 subd. 3). Demand the amount plus 1.5% per month interest, and note that a prevailing party in a civil action to collect the penalties must be awarded costs, disbursements and attorney fees. Keep the mechanic's lien notice and claim deadlines running in parallel. On public work, request payment information in writing: from 2026 (Laws 2026 ch. 90) the agency must give you the amount, date and pay application copy within 7 calendar days.

## Minnesota quirks to know

State agency interest does not apply to construction contractor claims (16A.124 subd. 5(e)), but municipalities owe 1.5% per month under 471.425. The same 5% / 60 / 10-day retainage rules appear twice, in 337.10 for private jobs and in 15.72 for public improvements (337.10 subd. 4(g) carves public agencies out). Federal- or state-aid projects: the agency need not pay the aided portion until the aid is received (15.72 subd. 2(h)). Maintenance or repair of production machinery and utility equipment is outside the definition of a building and construction contract.

## Worked example: retainage on a $480,000 subcontract in Minnesota

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | August 14, 2026 ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| GC pays the sub's share by | August 24, 2026 ([Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Minnesota private commercial job, $480,000 contract with the 5% maximum (337.10 subd. 4(b)): retainage is $24,000. Substantial completion 2026-06-15: the owner must release all retainage by 2026-08-14 (60 days, subd. 4(c)), less any permitted withholding (250% of correction costs; the greater of 1% of the contract, $4,800, or $500 until final paperwork). The GC then has 10 days, to 2026-08-24, to pay the sub's retainage. If the GC pays 30 days late, interest at 1.5% per month on $24,000 is about $360 (minimum $10 a month).

## Minnesota retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/minnesota/#calculator. The statutory figures it starts from:

- **Private job:** 60 days (Owner must release all retainage no later than 60 days after substantial completion (as defined in Minn. Stat. 541.051 subd. 1(a): sufficiently complete that the owner can occupy or use the improvement for its intended purpose). After substantial completion the owner may withhold no more than 250% of the cost to correct or complete known work, plus the greater of 1% of the contract value or $500 until final paperwork is submitted (paid within 60 days after submission). Retainage for warranty work is prohibited); then 10 days for the GC to pay the sub; interest: Late retainage to subs: 1.5% per month on undisputed amounts, minimum $10 (337.10 subd. 3, which covers payments under subd. 4).
- **Public job:** 60 days (Public contracting agency must release all retainage no later than 60 days after substantial completion; may then withhold no more than 250% of the cost to correct or complete known work and the greater of 1% of the contract value or $500 pending final paperwork; contractor pays subs' retainage within 10 days after receiving it. For streets, highways and bridges, substantial completion is when construction-related traffic devices and ongoing inspections are no longer required); then 10 days for the GC to pay the sub; interest: Subcontractor interest 1.5% per month (471.425 subd. 4a; 337.10 subd. 3). Agency interest on retainage is not stated in 15.72.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Minnesota retainage law: questions

### What is the maximum retainage in Minnesota?

5% on private contracts (Minn. Stat. 337.10 subd. 4(b)) and 5% of each progress payment on public improvements (15.72 subd. 2(a)).

### When must Minnesota retainage be released?

No later than 60 days after substantial completion, less 250% of known correction costs and the greater of 1% of the contract or $500 for outstanding paperwork (337.10 subd. 4(c), (e)).

## Sources

- [Minn. Stat. §337.10 subd. 4](https://www.revisor.mn.gov/statutes/cite/337.10)
- [Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Minnesota prompt payment law](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- Minnesota
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)
