title: "Mississippi Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Mississippi retainage: private jobs of $10K+ cap 5%, release within 60 days; public jobs cap 5%, release within 60 days. Statute and a calculator."
url: "/construction/retainage/mississippi/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Mississippi retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Mississippi retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Mississippi caps retainage on both private and public jobs at 5%. On private contracts over $10,000 entered into on or after July 1, 2024 (S.B. 2762, Miss. Code §87-9-3), no tier may hold more than 5% of the estimated value of work done and materials stored; excess is subject to 1% per month interest, and the owner must release retainage within 60 days after final completion once certificates of occupancy are issued. On public contracts, Miss. Code 31-5-33 fixes retainage at 5%, with half of it returned at 50% completion and 2.5% thereafter on contracts of $250,000 or more.

## Retainage on private jobs

| Rule | Mississippi law |
|---|---|
| Applies to | Contracts of $10,000 or more ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| Retainage cap | 5% of each payment ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| Release deadline | 60 days Owner must release retainage no later than 60 days after final completion of the contractor's work, provided all necessary certificates of occupancy have been issued; lower tiers are paid under the 15-day rule of Miss. Code 87-7-5. 'Final completion' includes punch list items, close-out documents, manuals and warranties ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| GC passes the sub's share within | 15 days of receiving it ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| Interest on late retainage | 1% per month on any amount retained above 5%, owed by the party that withheld it (S.B. 2762, 2024, section 1(2)); payer may still condition payment on receipt of payment from its own payer and on lien releases (pay-if-paid preserved) ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| Can the contract waive the rule? | No ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |

## Retainage on public jobs

| Rule | Mississippi law |
|---|---|
| Retainage cap | 5% of each payment ([Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm)) |
| Release deadline | 60 days Final payment is due at completion or substantial completion, beneficial use or occupancy, or certification of completion, whichever is first, with interest of 1% per month if unpaid after 60 calendar days (31-5-25). A contractor may substitute securities for retainage under 31-5-15 ([Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm)) |
| Prime passes the sub's share within | 15 days of receiving it ([Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm)) |
| Interest on late retainage | 1% per month on payments unpaid 60 calendar days after they were due; 0.5% per day on a prime's late payment to subs, capped at 15% ([Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm)) |
| Retainage bond in lieu | Contractor may, with surety consent, withdraw retainage by depositing U.S. Treasury obligations, Mississippi state or political subdivision bonds, or certain certificates of deposit with the treasurer (31-5-15) ([Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm)) |
| Applies to local governments | Yes ([Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm)) |

## When the GC says it hasn't been paid in Mississippi

The GC must pay subs pro rata on receipt: if the owner pays less than the full amount, the GC disburses what it receives proportionally among itself, its subs and suppliers (87-7-5; 31-5-27 for public work). The statute's 15-day penalty clock runs from the GC's receipt of payment from the owner, so a pay-if-paid clause can delay it. The 2024 retainage act expressly keeps pay-if-paid and lien-release conditions enforceable, so read your subcontract.

## After the deadline: what a sub can do in Mississippi

If the GC does not pay within 15 days after it is paid, demand the payment plus the 0.5% per day penalty (capped at 15%). For retainage on a private job entered after July 1, 2024, sue only the party in direct privity under S.B. 2762 section 1(6) for the amount plus 1% per month on any excess held; the prevailing party recovers attorney's fees, costs and expenses. Public job: claim on the payment bond and observe the notice deadlines under Miss. Code Title 31, chapter 5.

## Mississippi quirks to know

Private retainage rules cover contracts over $10,000 and exclude residential homebuilding and residential improvements of 16 or fewer units; lenders are not parties from whom interest can be claimed. The 5% retainage cap applies at every tier, and only the excess carries interest. Public retainage drops from 5% to 2.5% after the 50% mark on contracts of $250,000 or more and halves the held amount at that point. Mississippi Transportation Commission road and bridge contracts are outside 31-5-33.

## Worked example: retainage on a $480,000 subcontract in Mississippi

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | August 14, 2026 ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| GC pays the sub's share by | August 29, 2026 ([Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Mississippi private subcontract, $480,000, entered into after July 1, 2024: retainage capped at 5% = $24,000. If the contract held 10% ($48,000), the $24,000 excess would owe 1% per month, $240 per month. Final completion 2026-06-15 with certificates of occupancy issued: the owner must release by 2026-08-14 (60 days). The GC then has 15 days from receiving that payment, to 2026-08-29, to pay the sub; for a sub share of $24,000, each day later costs 0.5% = $120 a day, capped at 15% = $3,600 (Miss. Code 87-7-5).

## Mississippi retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/mississippi/#calculator. The statutory figures it starts from:

- **Private job:** 60 days (Owner must release retainage no later than 60 days after final completion of the contractor's work, provided all necessary certificates of occupancy have been issued; lower tiers are paid under the 15-day rule of Miss. Code 87-7-5. 'Final completion' includes punch list items, close-out documents, manuals and warranties); then 15 days for the GC to pay the sub; interest: 1% per month on any amount retained above 5%, owed by the party that withheld it (S.B. 2762, 2024, section 1(2)); payer may still condition payment on receipt of payment from its own payer and on lien releases (pay-if-paid preserved).
- **Public job:** 60 days (Final payment is due at completion or substantial completion, beneficial use or occupancy, or certification of completion, whichever is first, with interest of 1% per month if unpaid after 60 calendar days (31-5-25). A contractor may substitute securities for retainage under 31-5-15); then 15 days for the GC to pay the sub; interest: 1% per month on payments unpaid 60 calendar days after they were due; 0.5% per day on a prime's late payment to subs, capped at 15%.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Mississippi retainage law: questions

### What is the retainage cap on a Mississippi private construction contract?

5% of the estimated value of work properly done and materials stored, at every tier, for contracts over $10,000 entered into on or after July 1, 2024 (Miss. Code §87-9-3(2), added by S.B. 2762).

### When must Mississippi retainage be released on a private job?

No later than 60 days after final completion of the contractor's work, provided all necessary certificates of occupancy have been issued (Miss. Code §87-9-3(3), added by S.B. 2762).

### What retainage can a Mississippi public body hold?

5%; on contracts of $250,000 or more, half is returned at 50% completion if the work is on schedule and satisfactory, and future retainage drops to 2.5% (Miss. Code 31-5-33).

## Sources

- [Miss. Code Ann. §87-9-3 (added by Laws 2024, S.B. 2762, §1, eff. July 1, 2024)](https://billstatus.ls.state.ms.us/documents/2024/pdf/SB/2700-2799/SB2762SG.pdf) (mirror; the official site did not load)
- [Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Mississippi prompt payment law](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- Mississippi
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)