---
title: "Missouri Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Missouri retainage: no statute on private jobs, the subcontract governs; public jobs cap 10% under $50K, 5% above. Statute, release dates and a calculator."
url: "/construction/retainage/missouri/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Missouri retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Missouri retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Missouri caps retainage only on public works. Under RSMo 8.960, retainage on any public works contract or subcontract cannot exceed 5% (10% only on contracts estimated at $50,000 or less, which need no bond). The public owner pays at least 98% of the retainage, less authorised offsets, after substantial completion and acceptance, and the contractor must pay subs within 30 days of acceptance. On private jobs Missouri has no retainage statute: the contract sets the percentage and release date.

## Retainage on private jobs

**No statute.** Missouri has no statute that caps, requires or times retainage on private jobs. RSMo 431.180 only requires that scheduled payments be made as the contract says (with a court-awarded interest remedy of up to 1.5% per month), and retainage percentage and release date are whatever the contract provides. Sections 429.005 to 429.100 of the mechanic's lien chapter (read for this file) contain no retainage rule; later chapter 429 sections were not read.

## Retainage on public jobs

| Rule | Missouri law |
|---|---|
| Retainage cap | 10% on contracts under $50,000; 5% on contracts of $50,000 or more ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Release deadline | 30 days Public owner pays at least 98% of the retainage, less authorised offsets, to the contractor after substantial completion and acceptance; contractor pays subs within 30 days after acceptance (with invoice and documentation). If the owner gives no written explanation within 14 calendar days why the work is not substantially complete, it pays at least 98% of retainage within 30 days. Final payment is due on the earliest of completion with documentation filed, or architect/engineer or contracting authority certification, and must be paid within 30 days of the due date; 150% of the value of remaining minor items may be held ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Prime passes the sub's share within | 30 days of receiving it ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Interest on late retainage | 1.5% per month on payments not made within 30 days; subs: 1.5% per month after 15 days from the contractor's receipt (RSMo 8.960.1(5), (7)) ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Applies to local governments | Yes ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |

## When the GC says it hasn't been paid in Missouri

On private jobs, a contract term making a sub's payment contingent on the GC's receipt from a private owner is no defense to a mechanic's lien claim under chapter 429 (RSMo 431.183), but Missouri's private statute does not otherwise limit pay-if-paid. On public works, a contractor must pay subs pro rata on whatever it receives; when the owner rejects specific work in writing, only the subs responsible for that work go unpaid and all others are paid in full (RSMo 8.960.1(6)).

## After the deadline: what a sub can do in Missouri

Public job: claim 1.5% per month from the 16th day after the GC was paid and from the owner's day-30 for the prime; the contractor must separately identify and carry forward any amount it withholds from a sub in its next application (8.960.3). Private job: demand in writing and sue under RSMo 431.180.2 for up to 1.5% per month and attorney fees; keep the chapter 429 lien deadlines and, on residential property, the notice-of-rights requirement (429.016) running.

## Missouri quirks to know

The old 34.057 text now lives at 8.960 (transferred 2022). The public prompt-pay clock for subs runs 15 days from the contractor's receipt of payment and reaches every lower tier. Retainage released to subs is a separate 30-day clock after acceptance. The state's general supplier-invoice interest in RSMo 34.055 (45 days, prime plus 3 points) is for supplies and services and yields to 8.960 for public works. Missouri's DOT is carved out of 8.962 (delay-damages clauses).

## Worked example: retainage on a $480,000 subcontract in Missouri

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 15, 2026 ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| GC pays the sub's share by | August 14, 2026 ([RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Missouri public works contract, $480,000 (above $50,000, so 5% is the cap): retainage is $24,000. Project certified complete 2026-06-15 with documentation filed: final payment is due that day and must be paid within 30 days, by 2026-07-15, with at least 98% of the retainage (RSMo 8.960.1(4), (8)). If the owner pays 30 days late, interest at 1.5% per month on $24,000 is about $360. The contractor then pays the subs' retainage within 30 days after acceptance and within 15 days of receipt, or owes 1.5% per month (8.960.1(7)).

## Missouri retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/missouri/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 30 days (Public owner pays at least 98% of the retainage, less authorised offsets, to the contractor after substantial completion and acceptance; contractor pays subs within 30 days after acceptance (with invoice and documentation). If the owner gives no written explanation within 14 calendar days why the work is not substantially complete, it pays at least 98% of retainage within 30 days. Final payment is due on the earliest of completion with documentation filed, or architect/engineer or contracting authority certification, and must be paid within 30 days of the due date; 150% of the value of remaining minor items may be held); then 30 days for the GC to pay the sub; interest: 1.5% per month on payments not made within 30 days; subs: 1.5% per month after 15 days from the contractor's receipt (RSMo 8.960.1(5), (7)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Missouri retainage law: questions

### What is the maximum retainage on a Missouri public works contract?

5% of the contract or subcontract value (10% only if the contract is estimated at $50,000 or less and no bond is required) (RSMo 8.960.1(1)).

### Is there a retainage law for private construction in Missouri?

No. RSMo 431.180 requires payments per the contract and lets a court award up to 1.5% per month interest, but sets no retainage cap or release date.

## Sources

- [RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Missouri prompt payment law](https://fynex.ai/construction/prompt-payment/missouri/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- Missouri
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)
