Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Montana retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Montana retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

In Montana, retainage on a construction contract cannot exceed 5%, on private and public jobs alike (MCA 28-2-2110 and 18-2-316). The GC cannot hold more from you than the owner holds from the GC: the owner's retainage percentage is your ceiling. Retainage must be released on final acceptance of each portion of work that has its own price in the contract. Private statutes set no number of days for that release, so the date comes from your contract and from the owner's 21-day approval plus 7-day payment clock. Montana does not require owners to hold a lien-fund reserve. Residential work under $400,000 is outside Part 21.

## Retainage on private jobs

| Rule | Montana law |
|---|---|
| Retainage cap | 5% of each payment ([MCA 28-2-2110, 28-2-2103, 28-2-2104](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0100/0280-0020-0210-0100.html)) |
| Release deadline | Retainage must be released upon final acceptance of each portion of work for which the construction contract states a separate price (MCA 28-2-2110(3)). The statute sets no day count; the pay-request clock in 28-2-2103 and the 7-day pass-through then apply to the release payment. ([MCA 28-2-2110, 28-2-2103, 28-2-2104](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0100/0280-0020-0210-0100.html)) |
| GC passes the sub's share within | 7 days of receiving it ([MCA 28-2-2110, 28-2-2103, 28-2-2104](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0100/0280-0020-0210-0100.html)) |
| Interest on late retainage | 1 1/2% a month once a payment is more than 30 days late (MCA 28-2-2104) ([MCA 28-2-2110, 28-2-2103, 28-2-2104](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0100/0280-0020-0210-0100.html)) |

No statute makes the owner reserve a lien-fund percentage; Montana has no Texas-style required reserve. The 5% ceiling in 28-2-2110 is a cap, and the sub's cap equals whatever percentage the owner holds from the contractor. The statute does not say whether parties can contract around the cap.

## Retainage on public jobs

| Rule | Montana law |
|---|---|
| Retainage cap | 5% of each payment ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |
| Release deadline | 30 days Final acceptance of each separately priced portion (MCA 28-2-2110(3), which applies to government owners as well); on a building contract the government entity pays the final payment within 30 days after final acceptance (18-2-306). ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |
| Prime passes the sub's share within | 7 days of receiving it ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |
| Interest on late retainage | Late final payment by a government entity: rate in MCA 17-8-242 (0.05% per day for state agencies) or 18-1-404, as applicable (18-2-306(2)). ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |
| Applies to local governments | Yes ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |

## When the GC says it hasn't been paid in Montana

Montana's statute ties your 7 days to the GC being paid, not to the GC feeling like paying you. It does not mention pay-if-paid, and it says performance of the subcontract entitles you to payment from the contractor (28-2-2102(2)). You can ask the owner in writing to tell you what it has paid the GC on your work (28-2-2103(1)(g)). If the owner did pay and the GC did not pass it through, the 7 days have run and Part 21 interest starts to build once you are more than 30 days past the due date. Enforceability of pay-if-paid clauses is a case-law question not covered here.

## After the deadline: what a sub can do in Montana

1) Check your billing statement or invoice went to the GC: payment is not required under 28-2-2103(2) without it. 2) Send a written request to the owner under 28-2-2103(1)(g) for the date and amount paid to the GC. 3) Give the GC and the owner at least 7 calendar days written notice before suspending work; you may suspend and, if still unpaid 30 days after suspension, terminate (28-2-2117). Contract clauses that remove this right are void (28-2-2116(2)). 4) Demand 1.5% a month once more than 30 days late. 5) A suit to enforce the part carries fees to the winner (28-2-2105). Check lien and bond-claim deadlines separately: they are not in Part 21.

## Montana quirks to know

Part 21 reaches both private and public owners, because 18-2-123 sends public contractor and sub payment to the same part. The owner may disapprove only for the seven reasons in 28-2-2103(1)(c), and may withhold only enough to cover the direct expense of correcting them. Parties can lengthen the 21-day approval and 7-day payment periods only with the conspicuous 'Information for Bidders' notices in 28-2-2115. Out-of-state governing-law and venue clauses on Montana projects are void (28-2-2116(1)). Residential projects under $400,000 are exempt.

## Worked example: retainage on a $480,000 subcontract in Montana

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 15, 2026 ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |
| GC pays the sub's share by | July 22, 2026 ([MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Montana caps retainage at 5% (MCA 28-2-2110), so a $480,000 subcontract holds back at most $24,000. Assume the sub's final billing goes to the owner on 2026-06-15, the final payment request is deemed approved 21 days later (2026-07-06) and due 7 days after that (2026-07-13); the GC must then pay the sub within 7 days of receiving it. The statute sets no day count for retainage release beyond final acceptance of each priced portion, so this assumes release is tied to that final request. If the $24,000 is actually paid on 2026-09-11, 60 days late, it is more than 30 days past due, so interest runs from 2026-07-14 at 1.5% a month: $24,000 x 1.5% x 2 months = $720 (pro rata for the partial month). Illustration only; the due date depends on your contract.

## Montana retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/montana/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; then 7 days for the GC to pay the sub; interest: 1 1/2% a month once a payment is more than 30 days late (MCA 28-2-2104).
- **Public job:** 30 days (Final acceptance of each separately priced portion (MCA 28-2-2110(3), which applies to government owners as well); on a building contract the government entity pays the final payment within 30 days after final acceptance (18-2-306).); then 7 days for the GC to pay the sub; interest: Late final payment by a government entity: rate in MCA 17-8-242 (0.05% per day for state agencies) or 18-1-404, as applicable (18-2-306(2))..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Montana retainage law: questions

### What is the maximum retainage a GC can hold on a Montana subcontract?

5% at most on the contract, and no more than the percentage the owner holds from the GC (MCA 28-2-2110(1)-(2) for private work, 18-2-316 for public work). If the owner holds 5%, the GC may hold up to 5% from you; if the owner holds 0%, the GC may hold 0% from you.

## Sources

- [MCA 28-2-2110, 28-2-2103, 28-2-2104](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0100/0280-0020-0210-0100.html)
- [MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Montana prompt payment law](https://fynex.ai/construction/prompt-payment/montana/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- Montana
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)