Construction · Retainage law

Nevada retainage law: cap, release deadline and interest

On private work in Nevada, retention can be taken only if the agreement allows it, and it cannot exceed 5% of any payment, from owner to GC and from GC to sub (NRS 624.609, 624.624). The remaining balance is payable within 30 days after the owner occupies, uses, or has the work available for use (624.620). On public works, the public body holds 5% until the contract is 50% done, then may release it or hold at most 2.5% of later payments, and must pay quarterly interest on the retainage (NRS 338.515). Subs on public works follow the same 5%-until-50% rule against the GC (338.555) and the same against their own subs (338.595).

Also in Nevada: prompt payment law

Nevada retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Nevada law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Money remaining unpaid on the work of improvement is payable to the prime contractor within 30 days after the owner (or someone with the owner's authority) occupies or uses it, or after it is available for its intended use on written notice of availability or a certificate of occupancy (NRS 624.620(1)). Partial occupancy requires payment in proportion to the part occupied (624.620(5)).

Statute: Same 624.630 rate: higher of agreed rate or Nevada prime plus 4 percent, from the time the money becomes due

Owner releases by
July 15, 2026
GC pays the sub's share by
July 25, 2026
Days late
30
Interest owed
—
Total now owed
$24,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: NRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RuleNevada law
Retainage cap5% of each paymentNRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)
Release deadline30 days Money remaining unpaid on the work of improvement is payable to the prime contractor within 30 days after the owner (or someone with the owner's authority) occupies or uses it, or after it is available for its intended use on written notice of availability or a certificate of occupancy (NRS 624.620(1)). Partial occupancy requires payment in proportion to the part occupied (624.620(5)).NRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)
GC passes the sub's share within10 days of receiving itNRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)
Interest on late retainageSame 624.630 rate: higher of agreed rate or Nevada prime plus 4 percent, from the time the money becomes dueNRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)

Retention is only allowed if the agreement authorizes it, and then it 'must not exceed 5 percent of the amount of the payment' on each pay app, from owner to prime (624.609(2)(a)(1)) and from a higher-tier contractor to a lower-tier sub (624.624(2)(a)(1)). The statute does not set a separate release date for a sub's retainage; the sub's payment follows the 10-day-after-receipt clock in 624.624. Clauses waiving these rights are void (624.628(3)).

Retainage on public jobs

RuleNevada law
Retainage cap5% of each paymentNRS 338.515, 338.520, 338.525, 338.555, 338.595
Release deadline30 days Until 50% of the contract work is done the public body pays 95% and holds 5%. After 50% it may release retainage and stop withholding if satisfactory progress is being made; if it keeps withholding, the cap falls to 2.5% of each progress payment (after paying out half of the retainage held), or stays 5% if it is also withholding for contract non-compliance (NRS 338.515(1)-(4)). All remaining balance and retainage, plus interest, is due within 30 days after the public body occupies or uses the public work, or a notice of completion is recorded (338.520).NRS 338.515, 338.520, 338.525, 338.555, 338.595
Prime passes the sub's share within10 days of receiving itNRS 338.515, 338.520, 338.525, 338.555, 338.595
Interest on late retainagePublic body pays the contractor interest on withheld retainage each quarter at the rate quoted by at least three Nevada institutions as the highest paid on a ~90-day certificate of deposit on the first day of the quarter; amounts under $500 may be held until $500 accrues, four quarters pass, or retainage is due (NRS 338.515(6)). The contractor passes the sub's share of that interest down within 10 days (338.555(3)).NRS 338.515, 338.520, 338.525, 338.555, 338.595
Applies to local governmentsYesNRS 338.515, 338.520, 338.525, 338.555, 338.595

When the GC says it hasn't been paid in Nevada

Nevada limits pay-if-paid in practice. Even when a subcontract says the GC pays only if or when the owner pays, a sub that has not been paid within 45 days after the 25th of the month in which it submitted its request may stop work on 10 days' written notice (NRS 624.626(1)(b)). You can also ask the owner or any higher-tier contractor in writing for the date and amount of its payment and any withholding; they must answer within 5 days (624.628(5), and 5 working days for a public body or contractor on public works, 338.535 and 338.570). Lower-tier waivers of these rights are void (624.628(3)).

After the deadline: what a sub can do in Nevada

1) Send the written request for payment information (624.628(5)). 2) If you were not paid by the 624.624 date or given a proper withholding notice, give the higher-tier contractor written notice at least 10 days before stopping work; you may then terminate on at least 15 days' further written notice if still unpaid (624.626). 3) Copy the notice to other higher-tier contractors and the owner (624.628(2)). 4) Claim interest at the 624.630 rate. 5) The trier of fact may award your reasonable attorney's fees and collection costs (624.626(6)). Notices must go by personal delivery with a notarized statement, fax plus mail, certified mail, or the contract's method (624.628(4)). Keep lien deadlines separate.

Nevada quirks to know

Withholding must be justified in writing: an owner or GC that intends to withhold more than retention must serve a signed written notice by the payment due date naming the amount, the reason, and the contract or code section (NRS 624.609(3), 624.624(3)). Repair-cost withholding is limited to the amount exceeding 50% of the retention already held (624.609(2)(a)(2)(II)). A prime contractor must tell its subs in writing when it is paid (624.622(1)). Public work is carved out of the owner-to-prime sections (624.622(4)(b)) and governed by NRS 338 instead. A lien release can be demanded as a condition of payment (624.609(2)(b)).

Worked example: retainage on a $480,000 subcontract in Nevada

Subcontract$480,000
Retainage held5% = $24,000
CompletionJune 15, 2026
Private job: owner releases byJuly 15, 2026NRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)
GC pays the sub's share byJuly 25, 2026NRS 624.609(2)(a)(1), 624.620, 624.624(2)(a)(1), 624.628(3)
Interest if paid 30 days lateNo statutory rate; the contract governs

Nevada allows retention of at most 5% of each payment, so a $480,000 subcontract can hold back $24,000 (if the subcontract authorizes retention). Assume the owner occupies the building on 2026-06-15: the remaining balance is payable to the prime contractor within 30 days, by 2026-07-15 (NRS 624.620). The GC then owes the sub the earlier of the due date or 10 days after it is paid. Suppose the retainage is actually paid 60 days late. Interest runs at the higher of the contract rate or the prime rate at the largest bank in Nevada, as set by the Commissioner of Financial Institutions on the 1 January or 1 July before the agreement was signed, plus 4% (NRS 624.630). The statute prints no number, so the dollar amount depends on that published rate: each 1 percentage point of annual rate costs $24,000 x 1% x 60/365 = about $39.45, so the total is about $39.45 times (Nevada prime + 4), or times the contract rate if higher.

Run a payment like this in the split calculator

Nevada retainage law: questions

What is the maximum retainage on a private job in Nevada?

5% of each payment, and only if the agreement authorizes retention (NRS 624.609(2)(a)(1) for the owner, 624.624(2)(a)(1) for a GC withholding from a sub). The statute bars withholding more than the retention amount except for listed reasons with written notice (624.609(5)).

When must Nevada retainage be released after the job is done?

Money still unpaid on a private work of improvement is payable to the prime contractor within 30 days after owner occupancy or use, or after it is available for its intended use on notice of availability or a certificate of occupancy (NRS 624.620). On public works it is due within 30 days after use or occupancy or a recorded notice of completion (338.520).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

Book a demo