New Hampshire retainage law: cap, release deadline and interest
New Hampshire has no retainage statute for private work: no cap, no release deadline, no required lien-fund reserve. The percentage and release date come from your subcontract and the prime contract, so read the 'retainage' and 'final payment' clauses. For state agency contracts over $500,000, the contractor may swap retained cash for qualifying securities held by the state treasurer (RSA 21-I:20). State-funded water and wastewater projects have a specific rule, N.H. Admin. Code Env-Wq 507.12: 10% retainage until the project is 50% complete, none after, then 2% held through a one-year warranty.
Also in New Hampshire: prompt payment law
New Hampshire retainage release date and interest calculator
Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from New Hampshire law; change them if your contract or the statute's trigger differs.
Clock starts: New Hampshire has no statute capping or timing retainage on private projects, and no required lien-fund reserve percentage. Percentage, step-down and release date are whatever the prime contract and subcontract say. What the statute does add is RSA 447:8: a lienor who gives notice under 447:5-7 and sends the owner a written account every 30 days can require the owner to retain a sufficient sum of money to pay that claim, and the owner is not liable to the contractor for it unless the contractor first pays the claim.
The statute sets no fixed rate for this clock.
- Owner releases by
- —
- GC pays the sub's share by
- —
- Days late
- —
- Interest owed
- —
- Total now owed
- —
No statutory deadline for this clock: enter the days your contract sets.
Statute: N.H. RSA ch. 447
Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Retainage on private jobs
No statute. New Hampshire has no statute capping or timing retainage on private projects, and no required lien-fund reserve percentage. Percentage, step-down and release date are whatever the prime contract and subcontract say. What the statute does add is RSA 447:8: a lienor who gives notice under 447:5-7 and sends the owner a written account every 30 days can require the owner to retain a sufficient sum of money to pay that claim, and the owner is not liable to the contractor for it unless the contractor first pays the claim.
Retainage on public jobs
No statute. No New Hampshire statute read sets a retainage cap or release date for public contracts. Substitution of securities for retained funds: RSA 21-I:20 (state agency contracts over $500,000; initial deposit of at least $10,000; securities are certificates of deposit, US Treasury notes, certificates or bills, or state or local bonds or notes, each at least $5,000). That section covers state agencies only, not local governments. State-funded water and wastewater projects follow an administrative rule, not a statute: the recipient withholds 10% of partial payments until the project is 50% complete, withholds nothing more after 50%, then reduces retainage to 2% at substantial or final completion, held through the one-year warranty period and released after the recipient accepts the project (N.H. Admin. Code Env-Wq 507.12).
When the GC says it hasn't been paid in New Hampshire
Because the statute is silent, whether you must wait for the owner to pay the GC depends on the subcontract wording. A clause that makes owner payment a condition of the GC's duty to pay (pay-if-paid) is a contract question. The RSA 447 lien does not depend on the GC being paid: the owner must retain enough to cover a properly noticed claim, and is not liable to the contractor for that sum unless the contractor first pays the claim (RSA 447:8). Check your subcontract's payment clause and the deadlines in 447:5-6 for the notice to the owner.
After the deadline: what a sub can do in New Hampshire
1) Read the subcontract: due date, pay-if-paid language, notice and cure provisions, interest or late fee. 2) Send a written demand to the GC citing the contract due date. 3) On private work, serve the lien notices required by RSA 447:5-6 and send the owner the 30-day account (447:8). 4) On public work, file the lien within 90 days after completion and acceptance (447:15) and the bond claim within the same 90 days (447:17), then petition the superior court within one year of filing (447:18). 5) New Hampshire has no statutory interest rate for late construction payments; claim whatever the contract sets, or ask a court for interest on the debt.
New Hampshire quirks to know
New Hampshire is one of the states where payment timing is left almost entirely to contract; the state's construction payment law is its lien and bond statute, RSA 447. The only statutory retainage mechanism is the securities-in-lieu option for state contracts over $500,000 (RSA 21-I:20). Water and wastewater projects funded through the state follow the Env-Wq 507.12 retainage schedule by rule. Public-work lien and bond claims share a 90-day clock from completion and acceptance.
Worked example: retainage on a $480,000 subcontract in New Hampshire
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | June 15, 2026 |
| Release deadline | No statutory deadline in New Hampshire; the contract sets it |
New Hampshire has no statutory retainage rate for private work, so the only state-set schedule found is the state-funded water and wastewater rule, Env-Wq 507.12. On a $480,000 project under that rule, the recipient withholds 10% of partial payments until 50% of the project is complete: 10% of $240,000 = $24,000. After 50%, nothing more is withheld. At substantial completion on 2026-06-15 the retainage drops to 2% of the contract value, $9,600, held through the one-year warranty period and released after the recipient accepts the project, so no earlier than 2027-06-15. No statutory interest applies. On a private job the numbers come entirely from the contract.
New Hampshire retainage law: questions
Is there a retainage limit for private construction in New Hampshire?
No. The sections of the RSA read (ch. 447 and 21-I:20) contain no cap on private retainage, and no required release date. It is set by the contract.
Can I replace cash retainage with securities on a New Hampshire state contract?
Yes, for state agency contracts over $500,000 where the agency withholds a percentage until acceptance. You deposit qualifying securities with the state treasurer (initial deposit of at least $10,000, each security at least $5,000) and withdraw the equivalent cash retainage; the treasurer pays you the interest (RSA 21-I:20).
What is the retainage rule on state-funded water and wastewater projects in New Hampshire?
By administrative rule, the recipient withholds 10% of partial payments until the project is 50% complete, then no more; at substantial or final completion it reduces retainage to 2%, held during the one-year warranty period and released after acceptance (N.H. Admin. Code Env-Wq 507.12). This is a rule, not a statute.
Sources
Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.