Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states New York retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# New York retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

On private contracts of $150,000 or more, New York caps retainage at 5% of the contract sum, and a GC or sub can never hold more than the owner holds (General Business Law 756-c). The owner must release retainage within 30 days after final approval of the work, and a late owner or GC owes 1% a month from the date it was due. A contract clause requiring more than 5% is void (757(5)). On public jobs, the State and local owners hold up to 5% of each progress payment, or up to 10% if no performance and payment bonds are required, and the GC passes money to subs within 7 days (State Finance Law 139-f; General Municipal Law 106-b).

## Retainage on private jobs

| Rule | New York law |
|---|---|
| Applies to | Contracts of $150,000 or more ([N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)) |
| Retainage cap | 5% of each payment ([N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)) |
| Release deadline | 30 days Retainage must be released by the owner to the contractor no later than 30 days after final approval of the work under the construction contract (GBL 756-c). A contractor or sub must release a proportionate amount to the relevant parties after receiving retainage from the owner. ([N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)) |
| Interest on late retainage | one percent per month, running from the date the retention was due and owing, on the owner, contractor or sub that fails to release it ([N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)) |
| Can the contract waive the rule? | No ([N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)) |

## Retainage on public jobs

| Rule | New York law |
|---|---|
| Retainage cap | 5% of each payment ([N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |
| Release deadline | 30 days On substantial completion the contractor requisitions the remaining contract balance and the public owner pays it, less two times the value of items still to be completed and any claims, liens or judgments. The owner must give a written punch list within 45 business days after substantial completion and the contractor passes a sub's list down within 5 business days. As remaining items are corrected the owner pays for them on requisition. The contractor retains nothing from a sub's share of the remaining-balance payment (SFL 139-f(1), (1-a), (2); GML 106-b(1), (2)). ([N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |
| Prime passes the sub's share within | 7 days of receiving it ([N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |
| Interest on late retainage | Owner late to contractor: the Tax Law 1096(e) overpayment rate (SFL 179-g; GML 106-b(1)(c)). Contractor late to sub: one percent per month or fraction of a month (GBL 756-b(1)(b)). ([N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |
| Applies to local governments | Yes ([N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |

## When the GC says it hasn't been paid in New York

The private article does not expressly ban pay-if-paid, but it ties your 7 days to the GC's receipt of good funds and requires the GC to tell you, when you sign, the date it is due payment; if it does not disclose that date accurately, it owes you as though the owner had paid on the statutory dates (GBL 756-a(4)). You can ask in writing for the owner to notify you within 5 days of any payment to the GC. On public works, a pay-if-paid clause is invalid once the GC fails to submit a requisition for the remaining balance within 90 days of substantial completion (GML 106-b(2); SFL 139-f(2)).

## After the deadline: what a sub can do in New York

1) Check the dates: owner approval within 12 business days, payment 30 days after approval; GC pay-through within 7 days of good funds. 2) Send a written notice that payment for undisputed invoice amounts has not been received and that you intend to suspend; to the owner and GC for a sub, at least 10 calendar days before suspending (756-b(2)). 3) Demand 1% per month or fraction of a month from the day after the due date. 4) After 15 days from a complaint, you can refer the dispute to the American Arbitration Association for expedited arbitration, which the contract cannot take away (756-b(3); 757(3)). 5) Track separate Lien Law and bond-claim deadlines, including the Lien Law's trust-fund rules.

## New York quirks to know

The private act only applies where the project's aggregate cost is $150,000 or more, and excludes public works, small residential work and some subsidized housing. Interest is per month or fraction of a month, so partial months count whole. Retainage release is keyed to 'final approval of the work', not substantial completion. On State work where performance and payment bonds are dispensed with (small contracts), up to 20% may be retained until completion and acceptance (SFL 137(1), 139-f(4)); otherwise the 5% / 10% rule applies. Local owners waiting on budgeted State funds get until 10 days after the funds arrive (GML 106-b(1)(d)). Public interest is the Tax Law 1096(e) overpayment rate. The 7-day sub rule applies at every tier.

## Worked example: retainage on a $480,000 subcontract in New York

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | July 15, 2026 ([N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

A $480,000 private subcontract is above the $150,000 threshold, so retainage is capped at 5%: $24,000. Assume final approval of the work is given on 2026-06-15. The owner must release the retainage no later than 30 days after final approval, by 2026-07-15 (GBL 756-c), and the GC must release the sub's proportionate share after it receives the money. If the $24,000 is paid on 2026-09-13, 60 days late, interest is 1% per month from the due date: two months, $24,000 x 1% x 2 = $480 (the statute says 'per month', and the adjoining payment-interest rule counts a fraction of a month in full). The GC also owes its own late-payment interest on any sub payment that missed the 7-day clock.

## New York retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/new-york/#calculator. The statutory figures it starts from:

- **Private job:** 30 days (Retainage must be released by the owner to the contractor no later than 30 days after final approval of the work under the construction contract (GBL 756-c). A contractor or sub must release a proportionate amount to the relevant parties after receiving retainage from the owner.); interest: one percent per month, running from the date the retention was due and owing, on the owner, contractor or sub that fails to release it.
- **Public job:** 30 days (On substantial completion the contractor requisitions the remaining contract balance and the public owner pays it, less two times the value of items still to be completed and any claims, liens or judgments. The owner must give a written punch list within 45 business days after substantial completion and the contractor passes a sub's list down within 5 business days. As remaining items are corrected the owner pays for them on requisition. The contractor retains nothing from a sub's share of the remaining-balance payment (SFL 139-f(1), (1-a), (2); GML 106-b(1), (2)).); then 7 days for the GC to pay the sub; interest: Owner late to contractor: the Tax Law 1096(e) overpayment rate (SFL 179-g; GML 106-b(1)(c)). Contractor late to sub: one percent per month or fraction of a month (GBL 756-b(1)(b))..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## New York retainage law: questions

### What is the maximum retainage on a private construction contract in New York?

5% of the contract sum, and no more than the percentage the owner retains, on contracts of $150,000 or more. A contract requiring more than 5% is void as to the excess (Gen. Bus. Law 756-c, 757(5)).

### How long does a New York owner have to release retainage?

No later than 30 days after final approval of the work. If the owner or GC is late, it owes interest at 1% per month from the date the retainage was due (Gen. Bus. Law 756-c).

### What retainage can New York State or a municipality hold on public work?

Not more than 5% of each progress payment; up to 10% if there is no requirement for both a performance bond and a labor-and-material bond in the full contract amount (State Fin. Law 139-f(1); Gen. Mun. Law 106-b(1)(a)). The contractor may hold up to 5% from a sub, or up to 10% if the sub is unable or unwilling to bond (139-f(2)).

## Sources

- [N.Y. Gen. Bus. Law 756, 756-c, 757(5)](https://www.nysenate.gov/legislation/laws/GBS/756-C)
- [N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [New York prompt payment law](https://fynex.ai/construction/prompt-payment/new-york/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- New York
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)