North Carolina retainage law: cap, release deadline and interest
On North Carolina public construction contracts of $150,000 or more, retainage is capped at 5% of each periodic payment; under $150,000 no retainage is allowed at all (G.S. 143-134.1(b1)). The $150,000 floor took effect on 2026-06-19 (S.L. 2026-9, s. 5.1(c)); before that it was $100,000, and contracts already signed probably stay on the old floor. At 50% completion the owner can stop retaining; it must release all retainage within 60 days after a pay request and substantial completion or beneficial occupancy, keeping at most 2.5 times the value of unfinished or corrective work. Subs on public jobs get the same percentage as the owner holds from the prime. On private jobs North Carolina sets no cap or release date: a GC may hold a reasonable retainage not above the owner's initial percentage (G.S. 22C-4).
Also in North Carolina: prompt payment law
North Carolina retainage release date and interest calculator
Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from North Carolina law; change them if your contract or the statute's trigger differs.
Clock starts: Public construction contracts with total project costs under $150,000: no retainage allowed (the threshold was $100,000 until S.L. 2026-9, s. 5.1(c), effective 2026-06-19; contracts already in place before that date likely keep the $100,000 rule). At $150,000 or more: the owner may not retain more than 5% of any periodic payment. When the project is 50% complete, the owner, with the surety's written consent, may not retain more from periodic payments if the contractor continues to perform satisfactorily and has corrected written nonconformities (after which it may reinstate up to 5% if performance is unsatisfactory); an owner may instead keep total retainage at 2.5% through completion (b3). Within 60 days after submission of a pay request and (per the contract documents) receipt of the certificate of substantial completion or beneficial occupancy, the owner, with the surety's written consent, releases all retainage, but may keep up to two and one-half times the estimated value of the work still to be completed or corrected. Third-party claims and additive change orders are not a basis to delay release. Trades finished early (structural steel, piling, caisson, demolition and any listed in the bid documents) can be paid in full on line-item release with retainage cut to 0.5% of the contract, within 60 days of the request (143-134.1(b1), (b2), (b3)).
Statute: 1% per month or fraction thereof on amounts the prime contractor holds from a sub above the owner's percentage (143-134.1(b1)(3)). Interest on late periodic or final payments to the prime: 1% per month or fraction thereof from the due date or the 46th day for final payments (143-134.1(a)); interest is not stated for late release of retainage under (b1)(4).
- Owner releases by
- August 14, 2026
- GC pays the sub's share by
- August 21, 2026
- Days late
- 30
- Interest owed
- —
- Total now owed
- $24,000.00
No fixed statutory rate: enter the rate from the statute or your contract.
Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Retainage on private jobs
No statute. North Carolina has no statute capping the percentage of private-project retainage, setting a release date, or requiring a lien-fund reserve. The only rule is that a contractor may withhold from a sub 'a reasonable amount for retainage not to exceed the initial percentage retained by the owner' (G.S. 22C-4). The retainage percentage and release terms come from the contract; payments of retainage to subs fall within the 7-day pass-through of money the contractor receives (22C-3).
Retainage on public jobs
| Rule | North Carolina law |
|---|---|
| Retainage cap | 0% on contracts under $150,000; 5% on contracts of $150,000 or moreN.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
| Release deadline | 60 days Public construction contracts with total project costs under $150,000: no retainage allowed (the threshold was $100,000 until S.L. 2026-9, s. 5.1(c), effective 2026-06-19; contracts already in place before that date likely keep the $100,000 rule). At $150,000 or more: the owner may not retain more than 5% of any periodic payment. When the project is 50% complete, the owner, with the surety's written consent, may not retain more from periodic payments if the contractor continues to perform satisfactorily and has corrected written nonconformities (after which it may reinstate up to 5% if performance is unsatisfactory); an owner may instead keep total retainage at 2.5% through completion (b3). Within 60 days after submission of a pay request and (per the contract documents) receipt of the certificate of substantial completion or beneficial occupancy, the owner, with the surety's written consent, releases all retainage, but may keep up to two and one-half times the estimated value of the work still to be completed or corrected. Third-party claims and additive change orders are not a basis to delay release. Trades finished early (structural steel, piling, caisson, demolition and any listed in the bid documents) can be paid in full on line-item release with retainage cut to 0.5% of the contract, within 60 days of the request (143-134.1(b1), (b2), (b3)).N.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
| Prime passes the sub's share within | 7 days of receiving itN.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
| Interest on late retainage | 1% per month or fraction thereof on amounts the prime contractor holds from a sub above the owner's percentage (143-134.1(b1)(3)). Interest on late periodic or final payments to the prime: 1% per month or fraction thereof from the due date or the 46th day for final payments (143-134.1(a)); interest is not stated for late release of retainage under (b1)(4).N.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
| Applies to local governments | YesN.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
When the GC says it hasn't been paid in North Carolina
North Carolina has a plain rule here: payment by the owner to the contractor is not a condition precedent to payment of a subcontractor, and an agreement to the contrary is unenforceable (G.S. 22C-2). A GC cannot hide behind a pay-if-paid clause on a covered private job; its 7 days run from receipt of payment, but the sub's right to be paid is not conditioned on it. On public jobs the same 7-day rule applies on the prime's receipt of payment (143-134.1(b)). Residential jobs of 12 or fewer units are outside Chapter 22C.
After the deadline: what a sub can do in North Carolina
1) Confirm your work was performed in accordance with the subcontract and the GC received a periodic or final payment: the 7 days run from receipt. 2) Send a written demand citing G.S. 22C-3 and 22C-5, or 143-134.1(b) on a public job, with interest at 1% per month or fraction from the eighth day. 3) On a public job, ask the owner for the status of retainage: it must be released within 60 days after the pay request and substantial completion or beneficial occupancy (143-134.1(b1)(4)). 4) Keep lien (G.S. 44A) and bond-claim deadlines in view; they are separate and not covered here.
North Carolina quirks to know
Public retainage has a 50% step-down that needs the surety's written consent, a $150,000 floor below which no retainage is allowed, and line-item early release at 0.5% for structural steel, piling, caisson and demolition trades. Owners can hold up to 2.5 times the value of remaining work, but not for third-party claims or additive change orders. Department of Transportation contracts under G.S. 136-28.1 are outside the section. Early-release trades are paid within 60 days of the sub's request or on the surety's consent, whichever is later. S.L. 2026-9, s. 5.1(c) (H 1123, signed and effective 2026-06-19) raised the no-retainage floor from $100,000 to $150,000 of total project costs. The act has no transition clause; the UNC School of Government reads it as likely not reaching contracts already in place, so a contract signed before 2026-06-19 for $100,000 to $149,999 may still carry up to 5% retainage.
Worked example: retainage on a $480,000 subcontract in North Carolina
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | August 14, 2026N.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
| GC pays the sub's share by | August 21, 2026N.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19 |
| Interest if paid 30 days late | No statutory rate; the contract governs |
On a public prime contract of $480,000 (above $150,000) the owner may retain at most 5% of each periodic payment, up to $24,000 if it kept retaining to the end. Suppose it retains 5% until the contractor's gross invoices reach 50% of the contract ($240,000), which is $12,000, and then stops (with the surety's consent). Substantial completion is certified and the final pay request is submitted on 2026-06-15: all retainage is due within 60 days, by 2026-08-14 (143-134.1(b1)(4)). The prime must pay its sub's share within 7 days of receiving it. If the $12,000 is paid on 2026-10-13, 60 days late, and the 143-134.1(a) rate of 1% per month or fraction applies, interest is $12,000 x 1% x 2 = $240. The statute does not state interest for late retainage release specifically, so treat that figure as an estimate.
North Carolina retainage law: questions
Is there a retainage cap on North Carolina public projects?
Yes: 5% of any periodic payment, and only on public construction contracts with total project costs of $150,000 or more. Under $150,000, no retainage is allowed (G.S. 143-134.1(b1)). The floor was $100,000 until S.L. 2026-9 raised it, effective 2026-06-19; contracts already in place before then likely keep the $100,000 floor.
When must North Carolina retainage be released on a public job?
Within 60 days after the pay request is submitted and, per the contract documents, the owner receives a certificate of substantial completion or beneficial occupancy, with the surety's written consent. The owner may keep up to 2.5 times the estimated value of work still to be completed or corrected (143-134.1(b1)(4)).
Is there a limit on private retainage in North Carolina?
There is no stated percentage cap or release date. A contractor may hold back from a sub a reasonable amount for retainage not to exceed the initial percentage the owner retains (G.S. 22C-4).
Sources
Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.