North Dakota retainage law: cap, release deadline and interest

North Dakota allows a maximum retainage of 10% of each estimate until the project is 50% complete, and no further retainage after that, on both private contracts (N.D.C.C. 43-07-23) and public improvements (48-01.2-13), unless unsatisfactory progress is documented on a public job. On public work, at 95% completion the governing body may pay out up to 95% of what it has held, and final payment follows completion, acceptance and releases. There is no private release date or pass-through period in the statute, so your contract controls when a GC pays you.

Also in North Dakota: prompt payment law

North Dakota retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from North Dakota law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Retainage is 10% of each estimate until the project is 50% complete, then none unless unsatisfactory progress or performance is documented. The governing body may, on completion of 95% of the contract, pay up to 95% of the amount retained; the rest is paid in amounts and at times approved by the architect or engineer. Final payment of all money due follows completion, acceptance and delivery of releases (N.D.C.C. 48-01.2-13).

Statute: More than 30 days after approval of the estimate or the completion and acceptance date: interest at two percentage points below the Bank of North Dakota prime rate set 30 days from the estimate or completion date, until a warrant issues (48-01.2-14). Interest earned on invested retainage goes to the contractor at final payment (43-07-23; 48-01.2-13).

Owner releases by
July 15, 2026
GC pays the sub's share by
August 29, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: N.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RuleNorth Dakota law
Retainage cap10% of each paymentN.D.C.C. 43-07-23
How the cap appliesRetention of ten percent of each estimate is allowable until the project is fifty percent complete, with no further retainage on estimates during the continuance of the contract (N.D.C.C. 43-07-23).N.D.C.C. 43-07-23
Release deadlineThe section sets no release date. It says that if the owner, governing board or authorized committee invests retained funds, the interest earned is payable at final payment to the contractor on whose account the money was held.N.D.C.C. 43-07-23
Interest on late retainageNot set by statute

43-07-23 applies to contracts 'entered between persons for the performance of work to be done by a contractor', except those governed by 40-22-37 (municipal improvements), 48-01.2-13 (public improvements), or federal law. It reads as covering private owner-to-contractor contracts (and, by its wording, contractor-to-sub contracts). There is no statutory release deadline or pass-through period for private retainage, and no lien-fund reserve; release and interest on late release are governed by the contract. No pay-if-paid ban found.

Retainage on public jobs

RuleNorth Dakota law
Retainage cap10% of each paymentN.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37
Release deadline30 days Retainage is 10% of each estimate until the project is 50% complete, then none unless unsatisfactory progress or performance is documented. The governing body may, on completion of 95% of the contract, pay up to 95% of the amount retained; the rest is paid in amounts and at times approved by the architect or engineer. Final payment of all money due follows completion, acceptance and delivery of releases (N.D.C.C. 48-01.2-13).N.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37
Prime passes the sub's share within45 days of receiving itN.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37
Interest on late retainageMore than 30 days after approval of the estimate or the completion and acceptance date: interest at two percentage points below the Bank of North Dakota prime rate set 30 days from the estimate or completion date, until a warrant issues (48-01.2-14). Interest earned on invested retainage goes to the contractor at final payment (43-07-23; 48-01.2-13).N.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37
Applies to local governmentsYesN.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37

When the GC says it hasn't been paid in North Dakota

On a public job, the GC's 45 days run from the day the GC is paid by the public body (13-01.1-06), so the statute does depend on the GC having received money. Chapter 13-01.1 does not apply while a good-faith dispute over the amount or compliance is pending between the GC and its sub (13-01.1-05). On private jobs North Dakota's statutes do not address pay-if-paid at all, so the subcontract clause governs; check the payment and conditions precedent clauses.

After the deadline: what a sub can do in North Dakota

1) Public job: confirm the date the GC received payment from the public body, then count 45 days (13-01.1-06). 2) Send a written demand citing N.D.C.C. 13-01.1-06 and 13-01.1-02 interest at 1.75% per month. 3) Remember a documented dispute suspends the chapter until settled (13-01.1-05). 4) Public bond claim: a supplier of labor or material on a bonded public improvement who is not paid in full within 90 days after the last of the labor or material may sue on the bond, and suit on a claim must be commenced within one year after completion and acceptance (ch. 48-01.2 bond provisions). 5) Private job: rely on the contract, the mechanic's lien statute (N.D.C.C. ch. 35-27) and a demand letter; this file did not read ch. 35-27.

North Dakota quirks to know

North Dakota's retainage cap is one statute applied across private and public work, with a 50% step-down to zero. Interest on invested retainage belongs to the contractor. The prompt-pay interest rate is high (1.75% per month, 21% a year) and compounds. The 45-day sub payment clock counts from the GC's receipt of public money and can be varied by the contract between the GC and sub. The statute's definition of 'public improvement' excludes state highway and county road projects governed by other titles.

Worked example: retainage on a $480,000 subcontract in North Dakota

Subcontract$480,000
Retainage held10% = $48,000
CompletionJune 15, 2026
Public job: owner releases byJuly 15, 2026N.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37
GC pays the sub's share byAugust 29, 2026N.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37
Interest if paid 30 days lateNo statutory rate; the contract governs

On a $480,000 North Dakota subcontract, retainage is 10% of each estimate until the project is 50% complete: 10% of the first $240,000 = $24,000, then no more. On a public improvement, when the work reaches 95% the governing body may pay up to 95% of the amount held ($22,800), leaving $1,200 for final payment. Suppose completion and acceptance is 2026-06-15 and the GC receives the last public payment (including the sub's $24,000 retainage) on 2026-07-15. The GC then has 45 days, until 2026-08-29, to pay the sub (13-01.1-06). If it pays 60 days late, on 2026-10-28, interest at 1.75% per month is $24,000 x 1.75% x 2 = $840 (simple interest; the statute compounds unpaid interest after 45-day periods, so the true figure is a little higher). On a private job none of these dates apply and release is whatever the contract says.

Run a payment like this in the split calculator

North Dakota retainage law: questions

What is the retainage limit in North Dakota?

10% of each estimate until the project is 50% complete, with no further retainage during the rest of the contract (N.D.C.C. 43-07-23 for private contracts; 48-01.2-13 for public improvements). On public jobs, the governing body may add retainage again only if unsatisfactory progress or performance is documented.

When does North Dakota release public retainage?

At 95% completion the governing body may pay up to 95% of the retainage it has held; the rest is paid as the architect or engineer approves, and final payment follows completion, acceptance and delivery of necessary releases (48-01.2-13).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.