Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Ohio retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Ohio retainage law: cap, release deadline and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

On Ohio public improvements, partial payments must be at least 96% of the approved estimate, so retainage is capped at 4% for the whole job (R.C. 153.12, as rewritten by 2025 H.B. 96 from 2025-09-30; before that the owner held 8% of labor until 50% completion, and contracts bid before that date stay on the old rule). When the project is substantially completed and occupied, in use or accepted, the owner must pay the retained percentages plus interest within 30 days (withholding only what is reasonably needed for final completion), and the rest within 30 days of final completion (153.13). On private work Ohio sets no cap or release date for the owner, but a GC must pay subs their share of final retainage within 10 days of receiving it, with 18% interest (4113.61(A)(3)).

## Retainage on private jobs

| Rule | Ohio law |
|---|---|
| Retainage cap | No statutory cap; the contract sets the rate |
| Release deadline | No statutory cap, release date or owner-side clock on private projects. When a contractor receives final retainage from the owner, it must pay each sub and supplier its proportion within ten calendar days of receipt (or the contract period, if shorter), provided the contractor has determined the sub's work was satisfactory and the owner has approved it (R.C. 4113.61(A)(3)); the same rule applies down each tier (A)(4). ([Ohio Rev. Code 4113.61(A)(3), (A)(4), (D)](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| GC passes the sub's share within | 10 days of receiving it ([Ohio Rev. Code 4113.61(A)(3), (A)(4), (D)](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Interest on late retainage | eighteen per cent per annum of the retainage due, beginning the eleventh day after receipt of the retainage from the owner (4113.61(A)(3)) ([Ohio Rev. Code 4113.61(A)(3), (A)(4), (D)](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Can the contract waive the rule? | No ([Ohio Rev. Code 4113.61(A)(3), (A)(4), (D)](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |

Ohio sets no percentage cap and no owner-to-contractor release date for private retainage, and no lien-fund reserve. Retainage terms between the owner and contractor come from the contract. What the statute fixes is the pass-through of final retainage to subs and suppliers, with 18% interest and mandatory prevailing-party attorney fees.

## Retainage on public jobs

| Rule | Ohio law |
|---|---|
| Retainage cap | 4% of each payment ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |
| Release deadline | 30 days Partial payments are made at not less than 96% of the contractor's estimates approved by the architect or engineer (R.C. 153.12), i.e. retainage of no more than 4%. When the major portion of the project is substantially completed and occupied, in use or accepted, the retained percentages for that portion, plus interest accrued, are paid to the primary contractor within thirty days, withholding only the amount reasonably necessary to assure final completion. Funds held pending final completion, plus interest, are due no later than thirty days after final completion (153.13). These rules come from 2025 Am. Sub. H.B. 96, effective 2025-09-30, which replaced the old 8% hold on labor until 50% completion (then 100% payment) and the retainage escrow account. Law-firm summaries say contracts and bids due before 2025-09-30 stay under the old rules, and that payments for delivered materials are still made at 92% of invoice cost until the material is incorporated, so up to 8% of material value can be held until then. ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |
| Prime passes the sub's share within | 10 days of receiving it ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |
| Interest on late retainage | Interest accrues on retained funds and is paid with them (153.13). An unauthorized withholding of retainage, or payment not made within 30 days of an approved estimate, also earns interest at the average prime rate at commercial banks in the nearest city over 100,000 population (153.14). ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |
| Applies to local governments | Yes ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |

## When the GC says it hasn't been paid in Ohio

Ohio's 10 days run from the contractor's receipt of payment from the owner, so the statute assumes the GC has been paid. It does not by itself ban pay-if-paid; R.C. 4113.62(E) says a clause making a sub's payment contingent on another person's payment cannot stop the sub from filing a lien or bond claim before the deadlines expire. On public jobs, a sub cannot be paid at a lower rate than the public authority pays the contractor (153.12). Interest, attorney fee and court cost rights cannot be waived (4113.61(D)).

## After the deadline: what a sub can do in Ohio

1) Make sure you submitted your pay application in time for the GC to include it in its request (4113.61(A)(1)). 2) Confirm the date the GC received payment from the owner; ask the owner in writing. 3) Send a written demand citing R.C. 4113.61 with 18% interest from day 11. 4) If still unpaid 30 days after the payment was due, sue; the court awards interest and, to the prevailing party, reasonable attorney fees and costs unless it finds that inequitable (4113.61(B)). 5) Protect your lien or bond-claim rights under R.C. 1311 and 153.56 so waiting does not expire them (4113.62(E)). 6) Public job: payments unpaid 30 days after an approved estimate, or retainage withheld without authority, earn interest at the local commercial prime rate (153.14).

## Ohio quirks to know

The 18% interest and attorney-fee rights in 4113.61 are non-waivable, and apply down every tier and to wages (laborers must be paid within 10 days of payment or retainage). Residential work on single-, two- or three-family detached homes is excluded. The public retainage ceiling is expressed as a floor on payment (96%), not as a 'retainage cap'. Contracts that choose another state's law or venue, or waive surety bond rights, or waive claims on the basis of final payment when notice was received, are void (4113.62). The 4% public ceiling is new: 2025 H.B. 96 (effective 2025-09-30) replaced the old 8%-to-50%-then-zero labor retainage, deleted the retainage escrow account, and added the rule that no sub may be paid at a lower rate than the prime. Material deliveries are still paid at 92% until incorporated, per law-firm summaries of the act.

## Worked example: retainage on a $480,000 subcontract in Ohio

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 4% = $19,200 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 15, 2026 ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |
| GC pays the sub's share by | July 25, 2026 ([Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

On an Ohio public improvement, partial payments must be at least 96% of approved estimates (R.C. 153.12), so retainage on a $480,000 contract is at most 4% = $19,200. If the project is substantially complete and accepted on 2026-06-15, the owner must pay the retained percentages plus interest within 30 days, by 2026-07-15 (153.13), withholding only what is reasonably needed for final completion. The GC must pay the sub its share within 10 calendar days of receipt, by 2026-07-25 (4113.61(A)(3)). If it pays 60 days after that, on 2026-09-23, interest is 18% per annum from the eleventh day (2026-07-26): $19,200 x 18% x 60/365 = about $568. Assumes the whole $19,200 is the sub's share and is released in full; real jobs often hold some back for punch-list work.

## Ohio retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/ohio/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; then 10 days for the GC to pay the sub; interest: eighteen per cent per annum of the retainage due, beginning the eleventh day after receipt of the retainage from the owner (4113.61(A)(3)).
- **Public job:** 30 days (Partial payments are made at not less than 96% of the contractor's estimates approved by the architect or engineer (R.C. 153.12), i.e. retainage of no more than 4%. When the major portion of the project is substantially completed and occupied, in use or accepted, the retained percentages for that portion, plus interest accrued, are paid to the primary contractor within thirty days, withholding only the amount reasonably necessary to assure final completion. Funds held pending final completion, plus interest, are due no later than thirty days after final completion (153.13). These rules come from 2025 Am. Sub. H.B. 96, effective 2025-09-30, which replaced the old 8% hold on labor until 50% completion (then 100% payment) and the retainage escrow account. Law-firm summaries say contracts and bids due before 2025-09-30 stay under the old rules, and that payments for delivered materials are still made at 92% of invoice cost until the material is incorporated, so up to 8% of material value can be held until then.); then 10 days for the GC to pay the sub; interest: Interest accrues on retained funds and is paid with them (153.13). An unauthorized withholding of retainage, or payment not made within 30 days of an approved estimate, also earns interest at the average prime rate at commercial banks in the nearest city over 100,000 population (153.14)..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Ohio retainage law: questions

### What interest can an Ohio sub charge on late payment or retainage?

Eighteen per cent per annum of the payment or retainage due, starting on the eleventh day after the contractor receives payment from the owner (R.C. 4113.61(A)(1), (A)(3)). A sub may sue after payment is 30 days overdue, and the prevailing party recovers reasonable attorney fees and costs unless the court finds that inequitable.

### What is the retainage limit on Ohio public projects?

Partial payments must be made at not less than 96% of approved estimates, so retainage is effectively capped at 4% (R.C. 153.12). It is paid with interest within 30 days of substantial completion, occupation, use or acceptance, less what is needed for final completion (153.13).

### When must an Ohio GC pay a sub's share of final retainage?

Within ten calendar days after receiving the retainage from the owner, or the contract period if shorter, if the contractor has determined the sub's work was satisfactory and the owner has approved it (R.C. 4113.61(A)(3)).

### Is there a retainage cap on private projects in Ohio?

No statute read caps private retainage or sets a release date between owner and contractor; the contract does. Only the GC's pass-through of final retainage to subs is regulated (R.C. 4113.61(A)(3)).

### Did Ohio change public retainage in 2025?

Yes. 2025 Am. Sub. H.B. 96, effective 2025-09-30, requires partial payments of at least 96% of approved estimates throughout the project (a 4% ceiling), where the old rule was 92% until the job was 50% complete and 100% after. Retained amounts are due within 30 days of substantial completion, occupancy, use or acceptance (R.C. 153.12, 153.13). Contracts and bids due before 2025-09-30 stay under the old rules.

## Sources

- [Ohio Rev. Code 4113.61(A)(3), (A)(4), (D)](https://codes.ohio.gov/ohio-revised-code/section-4113.61)
- [Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Ohio prompt payment law](https://fynex.ai/construction/prompt-payment/ohio/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- Ohio
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)