Oklahoma retainage law: cap, release deadline and interest
On Oklahoma public construction contracts, retainage is up to 5% of each partial payment, reduced to 2.5% of the amount earned once the contractor is more than 50% complete and the agency finds satisfactory progress (61 O.S. 113.1, 226). The owner must release retainage within 21 calendar days after a certificate of substantial completion (less up to 150% of the cost to fix punch-list items), the prime passes subs' shares down within 10 days of receipt, and every other tier within 7 days. ODOT and the Turnpike Authority withhold none on their own contracts. Private jobs have no retainage statute: the contract decides.
Also in Oklahoma: prompt payment law
Oklahoma retainage release date and interest calculator
Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Oklahoma law; change them if your contract or the statute's trigger differs.
Clock starts: Up to 5% of all partial payments withheld as retainage; once the contractor has completed more than 50% of the total contract amount and the public agency has determined satisfactory progress, retainage is reduced to 2.5% of the amount earned (61 O.S. 113.1, version 2 of 2022; 226(A)). No later than 21 calendar days after a certificate of substantial completion for the project or a separate usable phase, and upon adequate performance and with approval of any applicable surety, the owner releases retainage to the prime contractor, less no more than 150% of the estimated cost to correct incomplete or defective work itemized on the certificate; remaining funds are released as each deficiency is corrected (226(C)).
Statute: Prime late to a sub: 1 1/2% per month (225(E)). Owner late on final payment: 1 1/2% per month (3/4% per month for school districts) from 30 days after completion and acceptance on lump-sum contracts, 60 days on unit-price contracts (113.3).
- Owner releases by
- July 6, 2026
- GC pays the sub's share by
- July 16, 2026
- Days late
- 30
- Interest owed
- —
- Total now owed
- $24,000.00
No fixed statutory rate: enter the rate from the statute or your contract.
Statute: 61 O.S. 113.1, 113.2, 113.3, 226
Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Retainage on private jobs
No statute. Oklahoma has no statute capping or timing retainage on private projects and none requiring a lien-fund reserve: 15 O.S. 820 and 821, read on OSCN, contain no retainage rule. The retainage percentage and release date come from the prime contract and subcontract. 15 O.S. 820 only sets the payment-frequency and default 28-day/10-day rules for private bid projects.
Retainage on public jobs
| Rule | Oklahoma law |
|---|---|
| Retainage cap | 5% of each payment61 O.S. 113.1, 113.2, 113.3, 226 |
| Release deadline | 21 days Up to 5% of all partial payments withheld as retainage; once the contractor has completed more than 50% of the total contract amount and the public agency has determined satisfactory progress, retainage is reduced to 2.5% of the amount earned (61 O.S. 113.1, version 2 of 2022; 226(A)). No later than 21 calendar days after a certificate of substantial completion for the project or a separate usable phase, and upon adequate performance and with approval of any applicable surety, the owner releases retainage to the prime contractor, less no more than 150% of the estimated cost to correct incomplete or defective work itemized on the certificate; remaining funds are released as each deficiency is corrected (226(C)).61 O.S. 113.1, 113.2, 113.3, 226 |
| Prime passes the sub's share within | 10 days of receiving it61 O.S. 113.1, 113.2, 113.3, 226 |
| Interest on late retainage | Prime late to a sub: 1 1/2% per month (225(E)). Owner late on final payment: 1 1/2% per month (3/4% per month for school districts) from 30 days after completion and acceptance on lump-sum contracts, 60 days on unit-price contracts (113.3).61 O.S. 113.1, 113.2, 113.3, 226 |
| Retainage bond in lieu | Allowed61 O.S. 113.1, 113.2, 113.3, 226 |
| Applies to local governments | Yes61 O.S. 113.1, 113.2, 113.3, 226 |
When the GC says it hasn't been paid in Oklahoma
Oklahoma's 10-day and 7-day pass-through clocks start when the prime or sub receives 'its corresponding payment' (61 O.S. 224). If the owner paid the prime, the 10 days have run; if the owner has not, a public prime can suspend work or terminate after 49 days (225(A)), and a sub is protected from owner-side interest only if the prime already paid it. The statutes do not mention pay-if-paid clauses; a contract provision that disallows or alters a sub's rights under the act is void (227(B)(2)).
After the deadline: what a sub can do in Oklahoma
1) Confirm the invoice was a 'proper invoice' and the date the prime received its corresponding payment. 2) Send a written demand citing 61 O.S. 224 and the 1.5%-per-month interest rate in 225(E). 3) On a private job, give 10 calendar days' written notice by certified mail before suspending work after payment is more than 10 days late (15 O.S. 820(C)). 4) On a public job, ask the owner about retainage release at the 21-day mark after the certificate of substantial completion (226(C)). 5) Claims against the bond for public work, and mechanic's lien deadlines, are separate; check Title 61 bond provisions and Title 42.
Oklahoma quirks to know
Section 113.1 exists in two co-existing 2022 versions (HB 4080 and SB 1520) with different wording on the 50% step-down; section 226 matches the SB 1520 wording. The Fair Pay for Construction Act excludes highway, railroad and turnpike construction, and one- to four-family dwelling contracts; the private-project statute (15 O.S. 820) also excludes one- to four-family dwellings (821(A)). A prime may suspend work or terminate on a public job 49 days after a proper invoice if unpaid. School districts pay 3/4% per month on late final payments instead of 1.5%. The Act voids out-of-state law and venue clauses (227(B)(1)).
Worked example: retainage on a $480,000 subcontract in Oklahoma
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 6, 202661 O.S. 113.1, 113.2, 113.3, 226 |
| GC pays the sub's share by | July 16, 202661 O.S. 113.1, 113.2, 113.3, 226 |
| Interest if paid 30 days late | No statutory rate; the contract governs |
On an Oklahoma public contract of $480,000, retainage can be up to 5% until the contractor passes 50% completion, then 2.5% of the amount earned: 5% of the first $240,000 = $12,000, plus 2.5% of the second $240,000 = $6,000, total $18,000 (full 5% would be $24,000). If the certificate of substantial completion issues on 2026-06-15, the owner must release the retainage by 2026-07-06 (21 days), less up to 150% of itemized punch-list costs. The prime must pass the sub's share within 10 days of receipt, by 2026-07-16. If it pays 60 days late, on 2026-09-14, interest at 1.5% per month on $18,000 is $18,000 x 1.5% x 2 = $540 (225(E)); interest on the owner's late release is not specified in 226.
Oklahoma retainage law: questions
What is the retainage limit on Oklahoma public construction contracts?
Up to 5% of each partial payment, dropping to 2.5% of the amount earned once the contractor is more than 50% complete and the public agency finds satisfactory progress (61 O.S. 113.1, 226(A)). For subcontracts, retainage cannot exceed 5% and falls to 2.5% of the original contract amount once the sub's work is at least 50% complete (226(B)).
When must Oklahoma retainage be released after substantial completion?
No later than 21 calendar days after a certificate of substantial completion, with surety approval and adequate performance, less no more than 150% of the estimated cost to correct itemized incomplete or defective work (61 O.S. 226(C)). The prime releases subs' shares within 10 days of receipt and all other entities within 7 days.