Construction · Retainage law

Oklahoma retainage law: cap, release deadline and interest

On Oklahoma public construction contracts, retainage is up to 5% of each partial payment, reduced to 2.5% of the amount earned once the contractor is more than 50% complete and the agency finds satisfactory progress (61 O.S. 113.1, 226). The owner must release retainage within 21 calendar days after a certificate of substantial completion (less up to 150% of the cost to fix punch-list items), the prime passes subs' shares down within 10 days of receipt, and every other tier within 7 days. ODOT and the Turnpike Authority withhold none on their own contracts. Private jobs have no retainage statute: the contract decides.

Also in Oklahoma: prompt payment law

Oklahoma retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Oklahoma law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Up to 5% of all partial payments withheld as retainage; once the contractor has completed more than 50% of the total contract amount and the public agency has determined satisfactory progress, retainage is reduced to 2.5% of the amount earned (61 O.S. 113.1, version 2 of 2022; 226(A)). No later than 21 calendar days after a certificate of substantial completion for the project or a separate usable phase, and upon adequate performance and with approval of any applicable surety, the owner releases retainage to the prime contractor, less no more than 150% of the estimated cost to correct incomplete or defective work itemized on the certificate; remaining funds are released as each deficiency is corrected (226(C)).

Statute: Prime late to a sub: 1 1/2% per month (225(E)). Owner late on final payment: 1 1/2% per month (3/4% per month for school districts) from 30 days after completion and acceptance on lump-sum contracts, 60 days on unit-price contracts (113.3).

Owner releases by
July 6, 2026
GC pays the sub's share by
July 16, 2026
Days late
30
Interest owed
—
Total now owed
$24,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: 61 O.S. 113.1, 113.2, 113.3, 226

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

No statute. Oklahoma has no statute capping or timing retainage on private projects and none requiring a lien-fund reserve: 15 O.S. 820 and 821, read on OSCN, contain no retainage rule. The retainage percentage and release date come from the prime contract and subcontract. 15 O.S. 820 only sets the payment-frequency and default 28-day/10-day rules for private bid projects.

Retainage on public jobs

RuleOklahoma law
Retainage cap5% of each payment61 O.S. 113.1, 113.2, 113.3, 226
Release deadline21 days Up to 5% of all partial payments withheld as retainage; once the contractor has completed more than 50% of the total contract amount and the public agency has determined satisfactory progress, retainage is reduced to 2.5% of the amount earned (61 O.S. 113.1, version 2 of 2022; 226(A)). No later than 21 calendar days after a certificate of substantial completion for the project or a separate usable phase, and upon adequate performance and with approval of any applicable surety, the owner releases retainage to the prime contractor, less no more than 150% of the estimated cost to correct incomplete or defective work itemized on the certificate; remaining funds are released as each deficiency is corrected (226(C)).61 O.S. 113.1, 113.2, 113.3, 226
Prime passes the sub's share within10 days of receiving it61 O.S. 113.1, 113.2, 113.3, 226
Interest on late retainagePrime late to a sub: 1 1/2% per month (225(E)). Owner late on final payment: 1 1/2% per month (3/4% per month for school districts) from 30 days after completion and acceptance on lump-sum contracts, 60 days on unit-price contracts (113.3).61 O.S. 113.1, 113.2, 113.3, 226
Retainage bond in lieuAllowed61 O.S. 113.1, 113.2, 113.3, 226
Applies to local governmentsYes61 O.S. 113.1, 113.2, 113.3, 226

When the GC says it hasn't been paid in Oklahoma

Oklahoma's 10-day and 7-day pass-through clocks start when the prime or sub receives 'its corresponding payment' (61 O.S. 224). If the owner paid the prime, the 10 days have run; if the owner has not, a public prime can suspend work or terminate after 49 days (225(A)), and a sub is protected from owner-side interest only if the prime already paid it. The statutes do not mention pay-if-paid clauses; a contract provision that disallows or alters a sub's rights under the act is void (227(B)(2)).

After the deadline: what a sub can do in Oklahoma

1) Confirm the invoice was a 'proper invoice' and the date the prime received its corresponding payment. 2) Send a written demand citing 61 O.S. 224 and the 1.5%-per-month interest rate in 225(E). 3) On a private job, give 10 calendar days' written notice by certified mail before suspending work after payment is more than 10 days late (15 O.S. 820(C)). 4) On a public job, ask the owner about retainage release at the 21-day mark after the certificate of substantial completion (226(C)). 5) Claims against the bond for public work, and mechanic's lien deadlines, are separate; check Title 61 bond provisions and Title 42.

Oklahoma quirks to know

Section 113.1 exists in two co-existing 2022 versions (HB 4080 and SB 1520) with different wording on the 50% step-down; section 226 matches the SB 1520 wording. The Fair Pay for Construction Act excludes highway, railroad and turnpike construction, and one- to four-family dwelling contracts; the private-project statute (15 O.S. 820) also excludes one- to four-family dwellings (821(A)). A prime may suspend work or terminate on a public job 49 days after a proper invoice if unpaid. School districts pay 3/4% per month on late final payments instead of 1.5%. The Act voids out-of-state law and venue clauses (227(B)(1)).

Worked example: retainage on a $480,000 subcontract in Oklahoma

Subcontract$480,000
Retainage held5% = $24,000
CompletionJune 15, 2026
Public job: owner releases byJuly 6, 202661 O.S. 113.1, 113.2, 113.3, 226
GC pays the sub's share byJuly 16, 202661 O.S. 113.1, 113.2, 113.3, 226
Interest if paid 30 days lateNo statutory rate; the contract governs

On an Oklahoma public contract of $480,000, retainage can be up to 5% until the contractor passes 50% completion, then 2.5% of the amount earned: 5% of the first $240,000 = $12,000, plus 2.5% of the second $240,000 = $6,000, total $18,000 (full 5% would be $24,000). If the certificate of substantial completion issues on 2026-06-15, the owner must release the retainage by 2026-07-06 (21 days), less up to 150% of itemized punch-list costs. The prime must pass the sub's share within 10 days of receipt, by 2026-07-16. If it pays 60 days late, on 2026-09-14, interest at 1.5% per month on $18,000 is $18,000 x 1.5% x 2 = $540 (225(E)); interest on the owner's late release is not specified in 226.

Run a payment like this in the split calculator

Oklahoma retainage law: questions

What is the retainage limit on Oklahoma public construction contracts?

Up to 5% of each partial payment, dropping to 2.5% of the amount earned once the contractor is more than 50% complete and the public agency finds satisfactory progress (61 O.S. 113.1, 226(A)). For subcontracts, retainage cannot exceed 5% and falls to 2.5% of the original contract amount once the sub's work is at least 50% complete (226(B)).

When must Oklahoma retainage be released after substantial completion?

No later than 21 calendar days after a certificate of substantial completion, with surety approval and adequate performance, less no more than 150% of the estimated cost to correct itemized incomplete or defective work (61 O.S. 226(C)). The prime releases subs' shares within 10 days of receipt and all other entities within 7 days.

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.