Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Oregon retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Oregon retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

In Oregon, retainage is capped at 5%, on private jobs (ORS 701.420) and on public improvements (ORS 279C.570(7)). Retainage is part of the final payment: interest of 1% per month on private final payments starts 30 days after the work is complete and accepted, and a public agency owes 1.5% per month from the same point (701.420(2); 279C.570(8)). On large commercial and public jobs you can substitute a surety bond for retainage, and the owner must accept it (701.435; 279C.560). A contractor that pays a sub in full gets the matching retainage released within 15 days of notice.

## Retainage on private jobs

| Rule | Oregon law |
|---|---|
| Retainage cap | 5% of each payment ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |
| Release deadline | 30 days Retainage is part of the final payment due the contractor or sub. Interest at 1% per month on the final payment runs from 30 days after the contractor or sub has completed and the owner has accepted the work; the party receiving the completion notice has 15 days to accept or list remaining work, otherwise interest starts 30 days after those 15 days. When a contractor pays a sub in full including retainage, the owner must pay the contractor the matching retainage within 15 days after notice, with 1% per month interest from 30 days after notice (ORS 701.420(2), (3)). ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |
| GC passes the sub's share within | 7 days of receiving it ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |
| Interest on late retainage | one percent per month on the final payment due the contractor or sub (ORS 701.420(2)); the contractor-to-sub late-payment rate under 701.630(6) is 1.5% a month or fraction ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |
| Escrow or bond instead of retainage | On a large commercial structure or public improvement contract a contractor may submit a surety bond in lieu of all or part of retainage, and the owner and lender must accept it; subs can request the same. If no bond is posted, the contractor may elect an interest-bearing account or interest on accumulated retainage at 2% plus the 90-day commercial paper discount rate (ORS 701.435). ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |

## Retainage on public jobs

| Rule | Oregon law |
|---|---|
| Retainage cap | 5% of each payment ([ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)) |
| Release deadline | 30 days The agency may reserve up to 5% of any progress payment. After 50% of the work is complete it may reduce or eliminate retainage on remaining monthly payments if work is progressing satisfactorily, only on the contractor's written application with the surety's written approval; at 97.5% completion it may, at its discretion, reduce retainage to 100% of the value of work remaining. Retainage held is included in and paid with the final payment (ORS 279C.570(7), (8)). ([ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)) |
| Prime passes the sub's share within | 10 days of receiving it ([ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)) |
| Interest on late retainage | 1.5% per month on final payment due the contractor, from 30 days after completion and acceptance (the contractor gives written notice of completion; the agency has 15 days to accept or list remaining work) until tendered (279C.570(8)). Contractor to sub: 9% per annum under 279C.515(2). ([ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)) |
| Retainage bond in lieu | Allowed ([ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)) |
| Applies to local governments | Yes ([ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)) |

## When the GC says it hasn't been paid in Oregon

Oregon's sub clock is triggered by the contractor receiving the owner's payment for your work, 7 days later on private jobs (701.630(2)) and 10 days later on public ones (279C.580(3)). A GC does not owe interest on a public job if the only reason it did not pay is that it was not paid in turn (279C.580(3)(d)). You can ask the owner in writing to tell you within 5 days after it pays the GC (701.625(12)). A sub that is not paid under 701.630(2) may suspend work on 3 days' written notice to the contractor and owner (701.635(2)).

## After the deadline: what a sub can do in Oregon

1) Confirm your billing and lien waiver went to the GC (payment is not required without them, 701.630(2)(b)). 2) Check the date the GC received the owner's payment; on a private job ask the owner under 701.625(12). 3) Send a written demand citing ORS 701.630 and 1.5% per month interest from day 8. 4) Suspend work on written notice if needed (3 days if the owner has not paid certified amounts or you are unpaid under 701.630(2); 7 days if the owner paid but the GC did not) (701.635). 5) The prevailing party in an action to collect interest recovers costs and attorney fees (701.630(7)). 6) On public work, a complaint can go to the Construction Contractors Board for non-payment (279C.515(3)). Lien and bond claim deadlines are separate.

## Oregon quirks to know

Oregon reads as one retainage ceiling (5%) shared by private and public work, enforced through the withholding rule that a lower tier cannot hold more than its contract allows. Billings are deemed certified 10 days after receipt unless the owner states reasons in writing. The disputed-amount withholding cap is 150% of the amount in dispute. Surety bonds in lieu of retainage must be accepted on large commercial structures and public improvements, and contractors can recover the added premium from the sub that asks for one. Public agency interest on progress payments floats at three times the 90-day commercial paper discount rate, up to 30%.

## Worked example: retainage on a $480,000 subcontract in Oregon

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | July 15, 2026 ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |
| GC pays the sub's share by | July 22, 2026 ([ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

On a private $480,000 subcontract Oregon caps retainage at 5% of the contract price of the work completed: $24,000 (ORS 701.420(1)). The work is complete and the owner accepts it on 2026-06-15; the owner's final payment (including the retainage) is due within 7 days of approval and interest at 1% per month runs from 30 days after acceptance, 2026-07-15. Suppose the GC receives the owner's final payment on 2026-07-15. It must pay the sub no later than 7 days later, 2026-07-22 (ORS 701.630(2)). If it pays 60 days late, on 2026-09-20, interest at 1.5% a month on $24,000 is $24,000 x 1.5% x 2 = $720 (701.630(6)), and the sub, as prevailing party in an action to collect that interest, recovers attorney fees. This ignores the billing and lien-waiver prerequisites in 701.630(2)(b).

## Oregon retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/oregon/#calculator. The statutory figures it starts from:

- **Private job:** 30 days (Retainage is part of the final payment due the contractor or sub. Interest at 1% per month on the final payment runs from 30 days after the contractor or sub has completed and the owner has accepted the work; the party receiving the completion notice has 15 days to accept or list remaining work, otherwise interest starts 30 days after those 15 days. When a contractor pays a sub in full including retainage, the owner must pay the contractor the matching retainage within 15 days after notice, with 1% per month interest from 30 days after notice (ORS 701.420(2), (3)).); then 7 days for the GC to pay the sub; interest: one percent per month on the final payment due the contractor or sub (ORS 701.420(2)); the contractor-to-sub late-payment rate under 701.630(6) is 1.5% a month or fraction.
- **Public job:** 30 days (The agency may reserve up to 5% of any progress payment. After 50% of the work is complete it may reduce or eliminate retainage on remaining monthly payments if work is progressing satisfactorily, only on the contractor's written application with the surety's written approval; at 97.5% completion it may, at its discretion, reduce retainage to 100% of the value of work remaining. Retainage held is included in and paid with the final payment (ORS 279C.570(7), (8)).); then 10 days for the GC to pay the sub; interest: 1.5% per month on final payment due the contractor, from 30 days after completion and acceptance (the contractor gives written notice of completion; the agency has 15 days to accept or list remaining work) until tendered (279C.570(8)). Contractor to sub: 9% per annum under 279C.515(2)..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Oregon retainage law: questions

### What is the maximum retainage in Oregon?

5%: not more than five percent of the contract price of the work completed (ORS 701.420(1)); public agencies may reserve not more than 5% of any progress payment (ORS 279C.570(7)).

### Can I give a surety bond instead of retainage in Oregon?

On a large commercial structure or a public improvement contract, a contractor can submit a surety bond in lieu of retainage and the owner and lender must accept it; a sub can request the same through the contractor, which must act within 30 days (ORS 701.435; 279C.560).

### What interest do Oregon public agencies pay on retainage and final payment?

1.5% per month on the final payment due the contractor, starting 30 days after completion and acceptance (ORS 279C.570(8)); retainage is paid as part of the final payment. On progress payments, interest is three times the 90-day commercial paper discount rate, capped at 30% (279C.570(2)).

## Sources

- [ORS 701.410, 701.420, 701.435, 701.630(5)](https://www.oregonlegislature.gov/bills_laws/ors/ors701.html#701.420)
- [ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Oregon prompt payment law](https://fynex.ai/construction/prompt-payment/oregon/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- Oregon
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)