Construction · Retainage law

Pennsylvania retainage law: cap, release deadline and interest

Pennsylvania caps retainage only on public contracts. Under the Procurement Code an agency may hold up to 10% of the amount due until the contract is 50% complete, then returns half of what it holds and limits further withholding to 5% of the value of completed work, with DGS contracts at 6% then 3% (62 Pa.C.S. §3921). At substantial completion the agency pays in full within 45 days, less 1.5 times the cost of punch items, with 10% a year interest if late (§3941), and the GC pays subs their retainage share within 20 days (§3922). On private jobs there is no cap, but the Contractor and Subcontractor Payment Act requires release within 30 days after final acceptance, and a 14-day pass-through (73 P.S. §509).

Also in Pennsylvania: prompt payment law

Pennsylvania retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Pennsylvania law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Retainage due to the contractor on final completion must be paid within 30 days after final acceptance of the work. If the owner holds no retainage, a contractor may hold retainage from a sub by agreement, payable within 30 days after final acceptance. A contractor or sub may seek earlier release after substantial completion of its own scope by posting a maintenance bond for 120% of the retainage held

Statute: Late or unreasonably withheld retainage bears interest at the §505(d) rate (1% per month or fraction of a month) from the date acceptance was unreasonably withheld or the retainage was due; plus the §512 penalty of 1% per month and attorney fees in a proceeding to recover it

Owner releases by
July 15, 2026
GC pays the sub's share by
July 29, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: 73 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RulePennsylvania law
Retainage capNo statutory cap; the contract sets the rate
Release deadline30 days Retainage due to the contractor on final completion must be paid within 30 days after final acceptance of the work. If the owner holds no retainage, a contractor may hold retainage from a sub by agreement, payable within 30 days after final acceptance. A contractor or sub may seek earlier release after substantial completion of its own scope by posting a maintenance bond for 120% of the retainage held73 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))
GC passes the sub's share within14 days of receiving it73 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))
Interest on late retainageLate or unreasonably withheld retainage bears interest at the §505(d) rate (1% per month or fraction of a month) from the date acceptance was unreasonably withheld or the retainage was due; plus the §512 penalty of 1% per month and attorney fees in a proceeding to recover it73 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))
Can the contract waive the rule?No73 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))

Pennsylvania sets no percentage cap on private-job retainage; the percentage is a contract term. The statute governs the release and pass-through clocks.

Retainage on public jobs

RulePennsylvania law
Retainage cap10% of each payment62 Pa.C.S. §§3902, 3921, 3922, 3933(c), 3938, 3941
Release deadline45 days Agencies generally: retainage up to 10% of the amount due until 50% of the contract is complete; at 50%, half the amount retained is returned (architect or engineer approval, satisfactory progress, no specific cause); afterwards no more than 5% of the value of completed work, and retained money may be held until substantial completion (at least 90% of the work done and certified). Extra retainage of 1.5 times possible liability may be held in a delay dispute between prime contractors unless bonded (§3921(a)). DGS contracts: up to 6% of total estimates until 50% is satisfactorily complete, then no more than 3% of the original contract amount (§3921(b)). Release: the architect or engineer makes final inspection within 30 days of the contractor's request; on substantial completion the agency pays in full within 45 days, less 1.5 times the certified cost of remaining minor items (§3941(a)).62 Pa.C.S. §§3902, 3921, 3922, 3933(c), 3938, 3941
Prime passes the sub's share within20 days of receiving it62 Pa.C.S. §§3902, 3921, 3922, 3933(c), 3938, 3941
Interest on late retainageFinal payment due after substantial completion bears interest from its due date at 10% per annum on contracts with retainage provisions (6% per annum without); where the agency issued bonds to finance the project, the bond rate or 10%, whichever is less, but not below the legal rate (62 Pa.C.S. §3941(b)).62 Pa.C.S. §§3902, 3921, 3922, 3933(c), 3938, 3941
Applies to local governmentsYes62 Pa.C.S. §§3902, 3921, 3922, 3933(c), 3938, 3941

When the GC says it hasn't been paid in Pennsylvania

Pennsylvania's Act ties a GC's duty to pay a sub to what the GC received, but does not make owner payment a condition precedent in the text read. The GC must disclose the owner's payment due date before the subcontract is signed; if it discloses it wrongly, it owes payment as though the owner had paid on time, except for delays outside its control such as change orders or weather (73 P.S. §507(b)). A GC may withhold for good-faith claims only if it gives the sub and owner written notice within the contract period or 14 calendar days, otherwise it waives the right (§511(b)). Pay-if-paid case law was not reviewed.

After the deadline: what a sub can do in Pennsylvania

Once 14 days pass after the GC's receipt of payment (or retainage), send a written demand citing 73 P.S. §507 or §509 for the amount plus 1% per month interest. If the sub is still unpaid 30 days after the end of the billing period, it can send written notice by email or mail, wait 30 more days, then give at least 10 days' certified-mail notice to the owner and suspend work without penalty (§507(e)). In arbitration or litigation the tribunal adds a penalty of 1% per month on wrongly withheld amounts, and the substantially prevailing party recovers a reasonable attorney fee (§512). On public jobs the equivalents are 62 Pa.C.S. §§3933 and 3935, with a bad-faith standard for the penalty and fees.

Pennsylvania quirks to know

The private Act cannot be waived by contract unless it says so (73 P.S. §503(c)) and does not cover projects of six or fewer residential units under construction at once. The public Procurement Code penalty and attorney fees require bad faith ('arbitrary or vexatious'), while the private Act's penalty and fees apply simply when the payment terms were not met and the withholding was not reasonably related to a good-faith claim (§512). Public retainage steps down at 50% completion: half of what was held is returned. A subcontractor's retainage clock follows final acceptance (30 days), not substantial completion, unless it posts the 120% maintenance bond. The public chapter covers only contracts over $50,000 and excludes PennDOT, distressed municipalities and school districts, Philadelphia PICA entities and transit authorities; a public project cannot be certified substantially complete until 90% of the work is done (62 Pa.C.S. §§3902, 3938).

Worked example: retainage on a $480,000 subcontract in Pennsylvania

Subcontract$480,000
Retainage held10% = $48,000
CompletionJune 15, 2026
Private job: owner releases byJuly 15, 202673 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))
GC pays the sub's share byJuly 29, 202673 P.S. §§509, 512, 503(c) (1994 Act 7, §§9, 12, 3(c))
Interest if paid 30 days lateNo statutory rate; the contract governs

Private job: Pennsylvania sets no cap, so assume the contract holds 10% ($48,000). If final acceptance is 2026-06-15, the retainage is due within 30 days, by 2026-07-15. The GC then has 14 days after receiving it to pay each sub (2026-07-29 if it was paid that day). If the owner pays two months late, interest at 1% per month is $48,000 x 1% x 2 = $960; in arbitration or court the tribunal adds a penalty of another 1% per month ($960) on wrongfully withheld sums, unless withheld under a good-faith claim, plus attorney fees. Public job (contract over $50,000): at 50% completion ($240,000 earned) up to 10% ($24,000) may be held; half ($12,000) is returned; after that no more than 5% of the value of completed work, so up to $24,000 (5% of $480,000) is held at the end. If the certificate of substantial completion issues 2026-06-15, full payment less 1.5 times punch-list costs is due within 45 days, by 2026-07-30 (§3941(a)); paid 30 days late, interest at 10% per annum on $24,000 is about $197.26 (§3941(b)). The GC owes subs their share within 20 days of receipt (§3922).

Run a payment like this in the split calculator

Pennsylvania retainage law: questions

When must retainage be paid in Pennsylvania?

Retainage due on final completion is payable within 30 days after final acceptance of the work, and a contractor must pay each sub its share within 14 days after receiving the retainage (73 P.S. §509(a), (c)). Public contracts have a separate cap (62 Pa.C.S. §3921).

What is the retainage cap on a Pennsylvania public contract?

Up to 10% of the amount due until 50% completion, then half the retained amount is returned and further withholding is capped at 5% of the value of completed work (62 Pa.C.S. §3921(a)). DGS contracts: 6% then 3% of the original contract amount (§3921(b)). At substantial completion the agency pays in full within 45 days, less 1.5 times the cost of remaining minor items (§3941(a)); subs get their retainage share within 20 days of the GC's receipt (§3922).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.