Construction · Retainage law

Texas retainage law: cap, release deadline and interest

Texas does not cap retainage on a private job and sets no deadline for paying it. What the statute does is make the owner reserve 10% of the contract price from the start of work until 30 days after completion (Prop. Code §53.101); that reserve is the pool that lien claimants (subs and suppliers) can reach. How much a GC holds back from a sub, and when it releases it, is a contract term. On public jobs of $400,000 or more the cap is 10% of the contract price below $5 million and 5% at $5 million or above (10% for dams), and a prime cannot hold a sub at a higher percentage than the agency holds the prime (Gov't Code §2252.032).

Also in Texas: prompt payment law

Texas retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Texas law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: The owner must reserve 10% of the contract price (or 10% of the value of the work done) while work is in progress and for 30 days after the work is completed. When the contract actually pays retainage out is set by the contract, not the statute.

Statute: No retainage-specific rate. Late payments that fall under Chapter 28 bear 1-1/2% per month (§28.004).

Owner releases by
—
Days late
—
Interest owed
—
Total now owed
—

No statutory deadline for this clock: enter the days your contract sets.

Statute: Tex. Prop. Code §§53.101-53.105; 28.002(b)

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RuleTexas law
Retainage capNo statutory cap; the contract sets the rate
Required reserveOwner must hold 10% of the contract price for 30 days after completionTex. Prop. Code §§53.101-53.105; 28.002(b)
Release deadlineThe owner must reserve 10% of the contract price (or 10% of the value of the work done) while work is in progress and for 30 days after the work is completed. When the contract actually pays retainage out is set by the contract, not the statute.Tex. Prop. Code §§53.101-53.105; 28.002(b)
GC passes the sub's share within7 days of receiving itTex. Prop. Code §§53.101-53.105; 28.002(b)
Interest on late retainageNo retainage-specific rate. Late payments that fall under Chapter 28 bear 1-1/2% per month (§28.004).Tex. Prop. Code §§53.101-53.105; 28.002(b)

Texas has no statutory cap on how much retainage a private contract may hold and no statutory deadline for paying it out. What the statute fixes is a 10%, 30-day owner reserve that secures lien claimants (§53.101). Payment timing is whatever the contract says, plus the Chapter 28 prompt-pay clocks.

Retainage on public jobs

RuleTexas law
Retainage cap10% on contracts under $5M; 5% on contracts of $5M or moreTex. Gov't Code §§2252.031-2252.033, 2251.022
Release deadlineNo fixed day count. The contract must state when the project is substantially complete and when all or part of retainage may be released for substantially completed or accepted portions. Retainage cannot be withheld after the prime finishes its work, including through the warranty period.Tex. Gov't Code §§2252.031-2252.033, 2251.022
Prime passes the sub's share within10 days of receiving itTex. Gov't Code §§2252.031-2252.033, 2251.022
Interest on late retainageInterest on retainage held in an interest-bearing account passes to the prime on completion (§2252.032(a)(3)); overdue payments accrue 1% plus WSJ prime (§2251.025)Tex. Gov't Code §§2252.031-2252.033, 2251.022
Applies to local governmentsYesTex. Gov't Code §§2252.031-2252.033, 2251.022

When the GC says it hasn't been paid in Texas

Texas has no blanket pay-if-paid ban, but a GC's "we haven't been paid" defence is limited by Bus. & Com. Code ch. 56. A contingent payment clause cannot be enforced if the owner's nonpayment is the GC's own fault (§56.051), after the sub sends a written objection notice (available after the 45th day following its payment request) (§56.052), or if enforcement would be unconscionable (§56.054). Chapter 56 does not apply to detached homes, duplexes, triplexes or quadruplexes, or to road and civil-engineering work (§56.002). The clause is an affirmative defence the GC must plead (§56.056).

After the deadline: what a sub can do in Texas

When the 7-day (private) or 10-day (public) pass-through lapses, document the date the GC was paid and send a written demand for the unpaid amount plus interest. On private non-residential jobs a sub can give written notice that it will suspend work on the 10th day after notice, copying the owner's lender where the statute's lender-notice conditions are met (Prop. Code §28.009); public subs have a parallel right through the vendor (Gov't Code §2251.052). A court may award reasonable attorney's fees under §28.005; on public contracts the losing side pays the winner's fees (§2251.043). Lien and bond deadlines (Prop. Code ch. 53; Gov't Code ch. 2253) run separately and are not extended by prompt-pay demands.

Texas quirks to know

Three details catch people. First, the retainage statute is an owner reserve for lien claimants, not a payment deadline: if the owner skips the 10% reserve, claimants get a lien to the extent it should have been held (§53.105). Second, public retainage rules do not apply to contracts under $400,000, to TxDOT highway contracts, or to contracts involving federal funds (§§2252.004, 2252.033). Third, an interest-bearing retainage account is optional for competitively bid contracts of $10 million or more and for non-competitive contracts (§2252.032(c)); the mandatory-escrow rule applies only to certain Texas Water Development Board projects (§2252.032(i)). Local governments (counties, municipalities, school districts, special districts) are covered by both public chapters.

Worked example: retainage on a $480,000 subcontract in Texas

Subcontract$480,000
Retainage held10% = $48,000
CompletionJune 15, 2026
Release deadlineNo statutory deadline in Texas; the contract sets it

Private job: 10% of $480,000 is $48,000. The owner's statutory reserve runs to 2026-07-15 (30 days after the 2026-06-15 completion). Assume the sub's final payment request, which includes the $48,000 retainage, reaches the owner on 2026-07-16 and the contract makes retainage payable then. The owner has 35 days, so payment is due 2026-08-20 and interest starts 2026-08-21. If the owner pays on 2026-10-20 (about two months late), interest at 1.5% per month is $48,000 x 1.5% x 2 = $1,440. The statute states the rate per month and does not say how to prorate a partial month. Public job of the same size: the 10% cap applies (contract is under $5 million and over the $400,000 floor), so up to $48,000 may be held; no statutory release day count exists, only the contract's substantial-completion terms.

Run a payment like this in the split calculator

Texas retainage law: questions

Is there a retainage cap on Texas private construction?

No. Texas sets no cap on contractual retainage between private parties. The only statutory figure is the owner's 10% reserve held for 30 days after completion for lien claimants (Prop. Code §53.101).

What is the retainage cap on a Texas public works contract?

10% of the contract price if the contract is under $5 million and 5% if it is $5 million or more, and 10% for dams. The rate cannot exceed the cap on any line of the schedule of values, and the statute does not apply below $400,000 (Gov't Code §§2252.032(b), 2252.033).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

Book a demo