Utah retainage law: cap, release deadline and interest
Utah caps retainage at 5% of each payment and 5% of the total construction price on nonresidential private jobs and on public jobs, for every tier from owner to GC to sub (Utah Code §13-8-5(3)). Retention must go into a separate interest-bearing account held in constructive trust, and must be released with its interest within 45 days after the latest of the contractor's billing statement, the certificate of occupancy or final acceptance, or acceptance of final pay quantities. A GC that receives retainage owes each sub its share within 10 days. Knowing, wrongful withholding costs 2% per month, and the winner collects attorney fees (§13-8-5(10)).
Also in Utah: prompt payment law
Utah retainage release date and interest calculator
Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Utah law; change them if your contract or the statute's trigger differs.
Clock starts: Retention and accrued interest must be released on the contractor's billing statement (with lien releases or waivers) within 45 days of the latest of: the owner receiving the statement, the certificate of occupancy or final acceptance notice, permitted occupancy or use without a certificate, or acceptance of final pay quantities
Statute: Retention must sit in a separate interest-bearing account, interest going to the contractor and subs; knowing and wrongful withholding carries a 2% per month charge on the withheld amount in addition to any other interest (§13-8-5(4), (10)(b))
- Owner releases by
- July 30, 2026
- GC pays the sub's share by
- August 9, 2026
- Days late
- 30
- Interest owed
- —
- Total now owed
- $24,000.00
No fixed statutory rate: enter the rate from the statute or your contract.
Statute: Utah Code §13-8-5
Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Retainage on private jobs
| Rule | Utah law |
|---|---|
| Retainage cap | 5% of each paymentUtah Code §13-8-5 |
| How the cap applies | A sub's retainage percentage must equal the owner-to-GC percentage whenever that percentage is below 5%, including when it is reduced mid-contract (§13-8-5(3)(c)). Total retention may not exceed 5% of the total construction price (§13-8-5(3)(b)).Utah Code §13-8-5 |
| Release deadline | 45 days Retention and accrued interest must be released on the contractor's billing statement (with lien releases or waivers) within 45 days of the latest of: the owner receiving the statement, the certificate of occupancy or final acceptance notice, permitted occupancy or use without a certificate, or acceptance of final pay quantitiesUtah Code §13-8-5 |
| GC passes the sub's share within | 10 days of receiving itUtah Code §13-8-5 |
| Interest on late retainage | Retention must sit in a separate interest-bearing account, interest going to the contractor and subs; knowing and wrongful withholding carries a 2% per month charge on the withheld amount in addition to any other interest (§13-8-5(4), (10)(b))Utah Code §13-8-5 |
| Escrow or bond instead of retainage | Required: retention must be placed in an interest-bearing account accounted for separately, held in constructive trust for the contractor and subs (§13-8-5(4))Utah Code §13-8-5 |
| Can the contract waive the rule? | NoUtah Code §13-8-5 |
Retainage on public jobs
| Rule | Utah law |
|---|---|
| Retainage cap | 5% of each paymentUtah Code §13-8-5 |
| Release deadline | 45 days Same as private: release within 45 days of the latest of the contractor's billing statement, certificate of occupancy or final acceptance notice, permitted use, or acceptance of final pay quantities; partial occupancy releases retention pro rataUtah Code §13-8-5 |
| Prime passes the sub's share within | 10 days of receiving itUtah Code §13-8-5 |
| Interest on late retainage | Retention is held in a separate interest-bearing account; interest is paid to the contractor and subs after the project is completed and accepted. Knowing wrongful withholding draws 2% per month (§13-8-5(4), (10))Utah Code §13-8-5 |
| Applies to local governments | YesUtah Code §13-8-5 |
When the GC says it hasn't been paid in Utah
Utah allows contingent-payment (pay-if-paid) contracts but limits them. A contingent payment clause is not a defense to a lien claim under the Preconstruction and Construction Liens chapter (Title 38, Chapter 1a), except on residential work of four units or fewer. A sub under a contingent payment contract can ask the contractor, before signing, for the financial information the contractor received about the project financing and the paying party, and the contractor must provide it (Utah Code §13-8-4(3)-(4)).
After the deadline: what a sub can do in Utah
If retainage is not released 45 days after the trigger, send a written demand that attaches the billing statement and lien waivers, and states the 45-day date, the amount and the 2% per month charge. The party who wrongly withheld retention knowingly owes that charge plus any other interest, and the successful party recovers attorney fees and costs (§13-8-5(10)). If a GC has been paid retainage and sits on a sub's share past 10 days, the same remedy applies. Lien rights run on separate deadlines in Utah Code Title 38, Chapter 1a, and a pay-if-paid clause does not defeat them.
Utah quirks to know
Section 13-8-5 applies only to nonresidential commercial or industrial work; on a mixed project it covers the nonresidential share pro rata by square footage (§13-8-5(1)(a)). It also allows an owner to hold up to twice the fair market value of unfinished work after substantial completion, with a written description of the incomplete work within 45 days (§13-8-5(8)). No waiver is allowed: no party may require another to waive the section (§13-8-5(11)). The local-government gap is notable, since Chapter 15-6 binds state agencies only, while §13-8-5 covers cities, counties and school districts. A version effective 1 January 2027 renumbers cross-references but leaves the retainage rules as read here.
Worked example: retainage on a $480,000 subcontract in Utah
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | July 30, 2026Utah Code §13-8-5 |
| GC pays the sub's share by | August 9, 2026Utah Code §13-8-5 |
| Interest if paid 30 days late | No statutory rate; the contract governs |
At the 5% cap, retention on a $480,000 nonresidential contract is $24,000 at most. If the certificate of occupancy issues on 2026-06-15 and the contractor submits its billing statement with lien waivers the same day, the owner or public agency must release the $24,000 and accrued interest by 2026-07-30 (45 days later). The GC must then pay each sub its share within 10 days of receiving the money. If the owner knowingly withholds for two months past 2026-07-30 (until 2026-09-30), the 2% per month charge is $24,000 x 2% x 2 = $960 in addition to interest, and the winning party also collects attorney fees. Public job under the Prompt Payment Act: a sub unpaid 45 days after the contractor is paid is owed 15.5% per annum from day 31.
Utah retainage law: questions
What is the maximum retainage in Utah?
5% of each payment and 5% of the total construction price, from owner or public agency to GC, GC to sub and sub to sub (Utah Code §13-8-5(3)). It applies to nonresidential commercial or industrial work.
How long does an owner have to release retainage in Utah?
45 days from the latest of the contractor's billing statement, the certificate of occupancy or final acceptance notice, permitted use, or acceptance of final pay quantities (Utah Code §13-8-5(5)). The billing statement must include lien releases or waivers.
How soon must a Utah GC pay a sub's share of released retainage?
Within 10 days after the GC receives all or any portion of the retention (Utah Code §13-8-5(9)). If the payment is designated for a particular sub, it goes to that sub.
What happens if retainage is wrongfully withheld in Utah?
A party who knowingly and wrongfully withholds retention owes 2% per month on the improperly withheld amount, on top of any other interest, and the successful party in a collection action recovers attorney fees and costs (Utah Code §13-8-5(10)).