Construction · Retainage law

Vermont retainage law: cap, release deadline and interest

Vermont does not cap the percentage of retainage but it does set the release clock. Retainage owed to the contractor on final completion must be paid within 30 days after final acceptance of the work, and a GC or sub that receives retainage must pay each lower tier within 7 days (9 V.S.A. §4005(a), (c)). A GC may hold retainage from a sub even when the owner holds none, but must still release it within 30 days after final acceptance (§4005(b)). Owners, contractors and subs that unreasonably withhold acceptance or fail to pay face interest, a 1% per month penalty and attorney's fees (§4005(d)). The chapter covers State and municipal owners too.

Also in Vermont: prompt payment law

Vermont retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Vermont law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Retainage due to the contractor on final completion must be paid within 30 days after final acceptance of the work. Where the owner holds no retainage, a GC or sub that holds retainage from its sub must also pay it within 30 days after final acceptance

Statute: An owner, GC or sub that unreasonably withholds acceptance or fails to pay retainage is subject to the interest, penalty (1% per month) and attorney's fee provisions of §§4002, 4003 and 4007

Owner releases by
July 15, 2026
GC pays the sub's share by
July 22, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: 9 V.S.A. §4005

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RuleVermont law
Retainage capNo statutory cap; the contract sets the rate
Release deadline30 days Retainage due to the contractor on final completion must be paid within 30 days after final acceptance of the work. Where the owner holds no retainage, a GC or sub that holds retainage from its sub must also pay it within 30 days after final acceptance9 V.S.A. §4005
GC passes the sub's share within7 days of receiving it9 V.S.A. §4005
Interest on late retainageAn owner, GC or sub that unreasonably withholds acceptance or fails to pay retainage is subject to the interest, penalty (1% per month) and attorney's fee provisions of §§4002, 4003 and 40079 V.S.A. §4005

Retainage on public jobs

RuleVermont law
Retainage capNo statutory cap
Release deadline30 days Same chapter as private: retainage is paid within 30 days after final acceptance of the work, and 'owner' includes the State, its subdivisions, municipalities and school districts9 V.S.A. §§4001(3), 4005
Prime passes the sub's share within7 days of receiving it9 V.S.A. §§4001(3), 4005
Interest on late retainageSame as private: interest under §4002/§4003 plus the 1% per month litigation penalty and attorney's fees (§4005(d), §4007)9 V.S.A. §§4001(3), 4005
Applies to local governmentsYes9 V.S.A. §§4001(3), 4005

9 V.S.A. chapter 102 sets no percentage cap on retainage, public or private. Whether a state agency's own statute or construction standard caps public retainage was not searched; within chapter 102 the contract sets the percentage.

When the GC says it hasn't been paid in Vermont

A Vermont GC cannot lean on the owner's late payment. A sub is entitled to payment from the party it contracts with once it performs (9 V.S.A. §4003(a)). Before a subcontract is signed, the GC must disclose the owner's actual payment due date; if it does not disclose accurately, the GC must pay the sub as though the owner had paid within the 20-day default (§4003(b)). The GC may still withhold the value of good-faith claims, such as defective work or third-party claims (§4007(a)). Disputed invoices must be challenged in writing within 10 working days or documentary errors are waived (§4004).

After the deadline: what a sub can do in Vermont

Check three dates: the end of the billing period (or invoice delivery), the day payment was received, and final acceptance for retainage. Then send a written demand citing §4002, §4003 or §4005, stating the amount and interest. If the payer still withholds, bring arbitration or a lawsuit: the arbitrator or court must award, as a penalty on top of damages, 1% per month on the sums wrongfully withheld, and the substantially prevailing party recovers reasonable attorney's fees and expenses (§4007(b)-(c)). Vermont also treats private-job payments received by a contractor as held in express trust for the project's subs and suppliers (§4005a). Lien rights are in a separate chapter.

Vermont quirks to know

The 20-day owner and 7-day GC clocks are defaults that the parties may vary by contract, except where the statute says 'notwithstanding any contrary agreement' (the GC's disclosure duty, the 7-day sub-tier payment, and the retainage pass-through). The interest rate points to 12 V.S.A. §2903(b), which on the current statute text no longer states a rate (§2903(c) sets 12% per annum for judgment liens), so the cross-reference needs checking. Materials delivered and accepted that carry a manufacturer's warranty or meet industry grades cannot be subject to retainage unless the supplier also installs them (§4005(e)). The statutory express trust under §4005a does not apply to federal, State or municipal projects.

Worked example: retainage on a $480,000 subcontract in Vermont

Subcontract$480,000
Retainage held10% = $48,000
CompletionJune 15, 2026
Private job: owner releases byJuly 15, 20269 V.S.A. §4005
GC pays the sub's share byJuly 22, 20269 V.S.A. §4005
Interest if paid 30 days lateNo statutory rate; the contract governs

Vermont sets no cap, so assume the contract holds 10% ($48,000). If final acceptance occurs on 2026-06-15, the retainage is due within 30 days, by 2026-07-15. A GC that receives it that day owes each sub its share by 2026-07-22 (7 days). If the owner pays two months late, on 2026-09-15, and the matter goes to arbitration or court, the 1% per month penalty is $48,000 x 1% x 2 = $960, in addition to interest under §4002(d) and attorney's fees. The same figures apply on a State or municipal job because the chapter's 'owner' includes those bodies.

Run a payment like this in the split calculator

Vermont retainage law: questions

When must Vermont retainage be released?

Within 30 days after final acceptance of the work (9 V.S.A. §4005(a)-(b)), and a GC or sub receiving retainage must pass each lower tier's share down within 7 days of receipt (§4005(c)).

Is there a retainage cap in Vermont?

No percentage cap appears in 9 V.S.A. chapter 102. The contract sets the percentage. The statute does bar retainage on delivered, accepted materials that carry a manufacturer's warranty or meet industry grades, except for a party that also installs them (§4005(e)).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

Book a demo