---
title: "Washington Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Washington retainage: no statute on private jobs, the subcontract governs; public jobs cap 5%, release within 60 days. Statute and a calculator."
url: "/construction/retainage/washington/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Washington retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Washington retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Washington regulates retainage only on public jobs. Public improvement contracts must reserve no more than 5% of the money earned as a trust fund for laborers, subs and suppliers, and the contractor may also hold back no more than 5% from each sub, paying the sub interest at the rate the contractor earns on it (RCW 60.28.011(1), (5)). Once all contract work is complete, the public body must release the retainage 60 days later, and the contractor can ask at any time to reduce retainage to 100% of the value of the work remaining. On private projects no retainage statute applies and the contract sets the rate and the release date.

## Retainage on private jobs

**No statute.** No Washington statute found that caps or schedules retainage on private projects; a search of the mechanic's-lien chapter (RCW 60.04) returned no retainage provision. Private retainage is whatever the owner-GC and GC-sub contracts say. The 5% rule, 60-day release and trust-fund treatment in RCW 60.28.011 are limited to public improvement contracts.

## Retainage on public jobs

| Rule | Washington law |
|---|---|
| Retainage cap | 5% of each payment ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| Release deadline | 60 days The contractor may ask for release once all contract work other than landscaping is complete; 60 days later the public body must pay all retainage (keeping 5% of earnings for landscaping), and in any case 60 days after completion of all contract work, subject to prevailing-wage releases and valid lien and tax claims ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| Prime passes the sub's share within | 10 days of receiving it ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| Interest on late retainage | At the contractor's option, retainage is held in a fund, in an interest-bearing account (interest goes to the contractor) or in escrow in bonds and securities. A prime that holds back a sub's retainage must pay the sub interest at the rate the prime earns on it (RCW 60.28.011(4)-(5)) ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| Retainage bond in lieu | Allowed ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| Applies to local governments | Yes ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |

## When the GC says it hasn't been paid in Washington

Washington's public-works pass-through duty runs from receipt of payment, not from the agency's final acceptance: the contractor or sub that is paid must pay each sub its share within 10 days (RCW 39.04.250(1)). A good-faith dispute lets a party withhold no more than 150% of the disputed amount, and everyone else in the chain is entitled to full and prompt payment of their portion, including released retainage (RCW 39.04.250(2)). For private projects the statutes read here do not address pay-if-paid; whether a contingent-payment clause is enforceable depends on the contract and case law, which was not reviewed.

## After the deadline: what a sub can do in Washington

On a public job, a sub that is paid late can claim interest for every month and portion of a month at the highest rate allowed under RCW 19.52.025, plus costs and attorneys' fees to the prevailing party (RCW 39.04.250(3)). To protect the retainage fund itself, a laborer, sub or supplier must file a lien notice within 45 days of completion of the contract work, and material suppliers must give the contractor the written notice in RCW 60.28.015. A lien action must be brought within four months of the claim filing (RCW 60.28.030). The prime's payment bond (ch. 39.08) is a separate route.

## Washington quirks to know

Washington treats public retainage as a statutory trust fund and gives claimants a lien on it (RCW 60.28.011(1)-(2)). Contractors may substitute a retainage bond for all or part of the retainage, and a sub can ask its prime to post a bond for the sub's share, which the prime must provide within 30 days unless the public body shows good cause (RCW 60.28.011(6)). Retainage on contracts funded by federal transportation money is replaced by reliance on the contract bond (RCW 60.28.011(1)(b)). Public bodies may not reserve anything from earnings other than this retainage (RCW 60.28.011(9)). Private projects have none of this.

## Worked example: retainage on a $480,000 subcontract in Washington

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | August 14, 2026 ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| GC pays the sub's share by | August 24, 2026 ([RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Public improvement contract: the cap is 5%, so at most $24,000 of the $480,000 can be reserved. With all contract work complete on 2026-06-15, the public body must pay the retainage by 2026-08-14 (60 days later), unless valid lien or tax claims are filed within the 45-day claim window, which closes 2026-07-30. The prime then has 10 days after receipt to pass each sub's share down (2026-08-24 if it was paid on the 14th). If the public body is two months late (paid 2026-10-14), the 1% per month rate on a $24,000 balance gives about $480 ($24,000 x 1% x 2). Private job of the same size: no Washington statute sets a cap, release date or interest, so the figures come only from the contract.

## Washington retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/washington/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 60 days (The contractor may ask for release once all contract work other than landscaping is complete; 60 days later the public body must pay all retainage (keeping 5% of earnings for landscaping), and in any case 60 days after completion of all contract work, subject to prevailing-wage releases and valid lien and tax claims); then 10 days for the GC to pay the sub; interest: At the contractor's option, retainage is held in a fund, in an interest-bearing account (interest goes to the contractor) or in escrow in bonds and securities. A prime that holds back a sub's retainage must pay the sub interest at the rate the prime earns on it (RCW 60.28.011(4)-(5)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Washington retainage law: questions

### What is the maximum retainage on a Washington public works contract?

5% of the money earned by the contractor, held as a trust fund for claims arising under the contract and certain state taxes (RCW 60.28.011(1)(a)). A contractor may also withhold up to 5% from a sub.

### How long does a Washington public body have to release retainage?

Sixty days after completion of all contract work, the public body must release and pay in full the retained amounts, subject to prevailing-wage and lien-claim releases (RCW 60.28.011(3)(b)). Landscaping can keep 5% of earnings longer.

### What interest can I claim if my retainage is held up on a Washington public job?

From a prime or sub who wrongfully withholds, interest at the highest rate allowed under RCW 19.52.025 for every month and portion of a month, plus costs and attorneys' fees to the prevailing party (RCW 39.04.250(3)). A public body that pays the prime late owes 1% per month, at least $1 (RCW 39.76.011).

## Sources

- [RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Washington prompt payment law](https://fynex.ai/construction/prompt-payment/washington/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- Washington
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)
