Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Wisconsin retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Wisconsin retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Wisconsin regulates retainage on public contracts only. On state construction contracts the state may retain no more than 5% of each estimate until the work is 50% complete, then retain nothing further unless progress is unsatisfactory, with total retainage never above 10% of the value of work completed. A prime must pay a sub's share of retainage, with the same 5% and 10% limits, within 7 calendar days after the prime is paid (Wis. Stat. §16.855(19)). Local public contracts of $1,000 or more follow the same 5% and 10% pattern (§66.0901(9)(b)). On private jobs no statute sets a percentage or release date.

## Retainage on private jobs

**No statute.** No Wisconsin statute found that caps retainage, requires release or sets interest on private construction. The percentage and release date are contract terms. The retainage rules found (Wis. Stat. §§16.855(19) and 66.0901(9)(b)) apply only to state and local public contracts.

## Retainage on public jobs

| Rule | Wisconsin law |
|---|---|
| Retainage cap | 5% of each payment ([Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21))) |
| Release deadline | State contracts: up to 5% of each estimate is retained until 50% of the work is complete; at 50% no more is withheld unless the department certifies unsatisfactory progress, and then total retainage may rise to no more than 10% of the value of work completed. On substantial completion, any amount retained shall be paid to the contractor, less the value of corrective or uncompleted work (16.855(19)(a)). On single-prime state projects, the general prime's retainage on mechanical, electrical and plumbing subcontracts follows the same 5% / 50% / 10% rule, is released on substantial completion of the sub's work, and every payment is due within 7 calendar days after the prime is paid (16.855(19)(b)). Local contracts of $1,000 or more (not DOT): same 5% / 50% / 10% pattern, amounts retained before 50% stay held, and retainage 'may be' paid on substantial completion, or against a bond or other collateral (66.0901(9)(b)). ([Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21))) |
| Prime passes the sub's share within | 7 days of receiving it ([Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21))) |
| Interest on late retainage | No interest on retainage itself found; a prime that pays a sub late owes interest at the §71.82(1)(a) rate compounded monthly from the 8th day after the prime is paid (§16.528(2m), §66.0135(3)) ([Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21))) |
| Applies to local governments | Yes ([Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21))) |

## When the GC says it hasn't been paid in Wisconsin

Under the public-work sections, the prime's duty to pay a sub runs from the prime's receipt of agency payment: payment is timely if made no later than 7 days after that receipt, and interest runs from the 8th day (Wis. Stat. §§16.528(2m), 66.0135(3)). A good-faith dispute exception applies if notice of the dispute is sent before the payment date. These sections do not address whether a pay-if-paid clause is enforceable on private or public jobs, which was not researched. On private jobs, §779.02(5) treats money received from an owner as a trust fund for unpaid claims.

## After the deadline: what a sub can do in Wisconsin

On a public job, count 7 days from the date the prime received agency payment, then send a written demand for the sub's share plus interest from the 8th day at the §71.82(1)(a) rate compounded monthly, citing §16.528(2m) or §66.0135(3). The prevailing party in an interest action recovers reasonable attorney fees (§§16.528(6), 66.0135(6)). Check that the dispute exception was not properly noticed. Private-job remedies are the contract, the lien chapter (Wis. Stat. ch. 779, with its own notice deadlines) and, for diverted funds, the trust-fund and theft rule in §779.02(5).

## Wisconsin quirks to know

Wisconsin pairs a retainage taper with a hard ceiling: 5% until half the work is done, then no more withholding, with a 10% total cap if the work is unsatisfactory. The sub-payment clock is only 7 days and the interest compounds monthly, but both are statutory for public contracts only. Local public contracts under $1,000 are outside the local retainage rule. Wisconsin's best-known private-job protection is not a payment deadline but the construction trust fund and theft provision in §779.02(5), which can reach responsible officers of a contractor that diverts owner payments.

## Worked example: retainage on a $480,000 subcontract in Wisconsin

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Release deadline | No statutory deadline in Wisconsin; the contract sets it |

State contract: 5% of $480,000 is $24,000 held until substantial completion. Suppose the prime receives the state's payment of the $24,000 retainage on 2026-06-15. The sub's share must reach the sub by 2026-06-22 (7 calendar days); interest starts 2026-06-23. If the sub is paid two months later (2026-08-23), interest at 12% per year compounded monthly is $24,000 x (1.01^2 - 1) = about $482. The state itself owes interest if it pays more than 30 days after a properly completed invoice. The 12% rate is printed in §71.82(1)(a), and §16.528(2m) makes it compound monthly. Private job: no statutory retainage rate, release date or interest; the contract controls.

## Wisconsin retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/wisconsin/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** no statutory deadline; then 7 days for the GC to pay the sub; interest: No interest on retainage itself found; a prime that pays a sub late owes interest at the §71.82(1)(a) rate compounded monthly from the 8th day after the prime is paid (§16.528(2m), §66.0135(3)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Wisconsin retainage law: questions

### What is the maximum retainage on a Wisconsin state construction contract?

5% of each estimate until the work is 50% complete, then no further withholding unless progress is unsatisfactory; the total may never exceed 10% of the value of work completed (Wis. Stat. §16.855(19)(a)).

## Sources

- [Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21))

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Wisconsin prompt payment law](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- Wisconsin
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)